You are here

Daily Road Report, April 10, 2019

For immediate release: April 9, 2019 - 3:00pm
TC19-309

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only. 
 
NEW 
 
SID BUCKWOLD BRIDGE NB & SB LANES RESTRICTED 
(Bridge upgrades) 
Lanes restricted in both directions; NB lanes zipper merge near 8th St: SB single lane starting at 20th St. 
Start: April 14, 8:30 a.m. End: October 31, 5:00 p.m. 
 
CIRCLE DR E NB & SB MEDIAN LANES CLOSED AT 14TH ST E 
(Guardrail work) 
Start: April 10, 9:00 a.m. End: April 11, 3:00 p.m. 
 
FEDORUK DR EB CLOSED FROM CENTRAL AVE TO KONIHOWSKI RD 
(Seeding) 
Start: April 10, 9:00 a.m. End: April 11, 5:00 p.m. 
 
ONGOING 
 
IDYLWYLD DR N NB & SB CURB LANES CLOSED AT CIRCLE DR E 
(Primary water main repair) 
Start: January 21, 7:00 a.m. End: April 29, 5:00 p.m. 
 
MCORMOND DR SB TRAFFIC REDUCED TO SINGLE LANE AT CROSSOVER; SB TRAFFIC USE OVERPASS TO ACCESS COLLEGE 
(Interchange work) 
Start: April 3, 1:00 p.m. End: July 31 5:00 p.m. 
 
BOYCHUK DR 2-WAY TRAFFIC ON NORTH SIDE OF INTERCHANGE AT HIGHWAY 16; NB LANE TEMP INTERSECTION   
(Interchange construction)  
Start: September 30, 2018 12:00 a.m. End: July 31, 2019, 5:00 p.m.   
   
MCORMOND DR SINGLE LANE NB & SB FROM KERR RD TO HIGHWAY 5 
(Interchange Construction) 
Start: November 14, 8:00 a.m. End: July 31, 5:00 p.m. 
 
AVE H S INTERSECTION CLOSED AT 11TH ST W 
(Construction) 
Start: March 11, 7:00 a.m. End: August 31, 5:00 p.m. 
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances. 
Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.