Daily Road Report, April 17

For immediate release: April 16, 2018 - 3:00pm
TU18-273

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.

NEW

PRESTON AVE S NB MEDIAN LANE CLOSED AT MAIN ST
(sewer inspection)
Start: April 17, 9:00 a.m. End: April 17, 11:00 a.m.

CLARENCE AVE S SB LANES CLOSED FROM CASCADE ST TO WILSON CRES
(light installation)
Start: April 17, 9:00 a.m. End: April 17, 12:00 p.m.

IDYLWYLD DR S SB OFF RAMP CLOSED AT RUTH ST W
(overhead sign replacement)
Start: April 17, 9:00 a.m. End: April 17 3:00 p.m.

20TH ST W NB & EB CURB LANES CLOSED AT AVE P S
(sewer inspection)
Start: April 17, 11:00 a.m. End: April 17, 1:00 p.m.

4TH AVE S NB LANES CLOSED FROM 21ST ST E TO 22ND ST E
(transformer installation)
Start: April 17, 6:00 p.m. End: April 17, 8:30 p.m.

ONGOING

IDYLWYLD DR S SB EXIT LANE CLOSED AT RUTH ST W
(overhead sign replacement)
(OFF RAMP closed on Tuesday, April 17)
Start: April 16, 9:00 a.m. End: April 19, 3:00 p.m.

HIGHWAY 5 WB ROAD CLOSED AT MCORMOND DR
(girder erection)
Two-way traffic will be accommodated in the EB lanes.
Start: April 4, 6:00 p.m. End: April 18, 7:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.

Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.