You are here

Daily Road Report, August 16

For immediate release: August 15, 2018 - 3:00pm
TU18-475

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.

NEW

RUTH ST E EB & WB MEDIAN LANES CLOSED AT DUFFERIN AVE
(sewer lining)
Start: August 16, 7:00 a.m. End: August 16, 4:00 p.m.

IDYLWYLD DR N NB &SB MEDIAN LANES CLOSED AT 25TH ST E
(railway maintenance)
Start: August 16, 9:00 a.m. End: August 16, 3:00 p.m.

CLARENCE AVE S NB CURB LANE CLOSED FROM 14TH ST E TO 15TH ST E
(sewer lining)
Start: August 16, 9:00 a.m. End: August 16, 5:00 p.m.

AVE C S ROAD CLOSED FROM 21ST ST W TO 22ND ST W
(water & sewer replacement)
Start: August 16, 9:00 a.m. End: August 18, 4:00 p.m.

RUTH ST E EB PARKING LANE CLOSED THROUGH THE INTERSECTIONS FROM WILSON CRES TO NORMAN CRES
(sewer lining)
Start: August 16, 10:00 a.m. End: August 17, 5:00 p.m.

NIGHTWORK

22ND ST W WB CURB & CENTRE LANE CLOSED FROM IDYLWYLD DR S TO AVE H S
(micro-surfacing)
Start: August 15, 7:00 p.m. End: August 16, 7:00 a.m.

22ND ST W EB MEDIAN & CENTRE LANES CLOSED FROM AVE H S TO IDYLWYLD DR S
(micro-surfacing)
Start: August 15, 7:00 p.m. End: August 16, 7:00 a.m.

CIRCLE DR E CENTER LANE CLOSED AT CLARENCE AVE S
(pavement markings)
Start: August 15, 7:00 p.m. End: August 16, 7:00 a.m.

22ND ST W EB CURB & CENTRE LANES CLOSED FROM AVE H S TO IDYLWYLD DR S
(micro-surfacing)
Start: August 16, 7:00 p.m. End: August 17, 7:00 a.m.

CIRCLE DR E SB CURB LANE CLOSED AT TAYLOR ST E
(pavement markings)
Start: August 16, 7:00 p.m. End: August 17, 7:00 a.m.

ONGOING

MCKERCHER DR NB CLOSED FROM HOLLAND RD TO PARKDALE RD
(valve repair)
Start: August 15, 9:00 a.m. End: August 16, 4:00 p.m.

IDYLWYLD DR S NB & SB MEDIAN LANES CLOSED SOUTH OF SID BUCKWOLD BRIDGE
(pedestrian bridge repairs)
Start: July 30, 9:00 a.m. End: August 16, 7:00 p.m.

IDYLWYLD DR N SB CURB LANE CLOSED SOUTH OF AVE C
(guard rail installation)
Start: August 13, 9:00 a.m. End: August 17, 3:00 p.m.

COLLEGE DR WB LANES CLOSED AT MCORMOND DR
(bridge construction)
Two-way traffic maintained in EB lanes
Start: August 13, 5:00 a.m. End: August 19, 4:00 p.m.

RUTH ST E EB PARKING LANE CLOSED FROM HAULTAIN AVE TO CAIRNS AVE
(sidewalk replacement)
Start: August 14, 8:00 a.m. End: August 20, 4:00 p.m.

TAYLOR ST E EB CURB LANE CLOSED AT ARLINGTON AVE
(intersection improvements)
Start: August 13, 7:00 a.m. End: August 31, 5:00 p.m.

CIRCLE DR E SB CURB & CENTER LANES CLOSED AT 8TH ST E
(water main maintenance)
Start: July 30, 9:00 a.m. End: September 14, 5:00 p.m.

COLLEGE DR SPEED REDUCTION FROM CENTRAL AVE TO CIRCLE DR E
(ditch excavation)
Start: July 26, 9:00 a.m. End: September 14, 6:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

NEAULT RD NB & SB SPEED REDUCTION FROM 33RD ST W & KENSINGTON GATE W
(water main installation)
Start: August 15, 7:00 a.m. END: October 15, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.

Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.