You are here

Daily Road Report, August 30

For immediate release: August 29, 2018 - 3:00pm
TU18-496

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.

NEW

COLLEGE DRIVE EB ROAD CLOSED AT MCORMOND DR
(bridge construction)
Two-way traffic will be accommodated in the WB lanes.
Start: August 30, 5:00 a.m. End: September 7, 5:00 p.m.

BROADWAY AVE SB LANES CLOSED & NB MEDIAN LANE CLOSED FROM 4TH ST E TO 3RD ST E
(water & sewer connection)
Start: August 30, 8:00 a.m. End: August 31, 6:00 p.m.

2ND AVE S AND 3RD AVE S CLOSED FROM 19TH ST TO SPADINA CRES; SPADINA CRES CLOSED FROM 2ND S TO 3RD AVE S
(Fireworks Festival)
Start: August 30, 8:00 a.m. End: September 3, 12:00 p.m.

CENTRAL AVE NB MEDIAN LANE CLOSED AT 115TH ST W
(CCTV inspections)
Start: August 30, 9:00 a.m. End: August 30, 1:00 p.m.

IDYLWYLD DR N SB CURB LANE CLOSED AT 37TH ST W
(microsurfacing)
Start: August 30, 9:00 a.m. End: August 30, 3:30 p.m.

CIRCLE DR W SB MEDIAN LANE CLOSED FROM 33RD ST W TO LAURIER DR
(pothole patching)
Start: August 30, 10:00 a.m. End: August 30, 4:00 p.m.

IDYLWYLD DR N SB CURB LANE CLOSED FROM 33RD ST E TO 32ND ST W
(pole replacement)
Start: August 30, 11:00 a.m. End: August 30, 2:00 p.m.

NIGHTWORK

SPADINA CRES E ROAD CLOSED FROM QUEEN ST TO 24TH ST E
(bridge repairs)
Start: August 29, 9:00 p.m. End: August 30, 6:00 a.m.

ONGOING

IDYLWYLD DR N NB & SB MEDIAN LANES CLOSED FROM AVE C N TO 51ST ST E
(chain link fence repair)
Start: August 28, 9:00 a.m. End: August 30, 3:30 p.m.

TAYLOR ST E EB CURB LANE CLOSED AT ARLINGTON AVE
(intersection improvements)
Start: August 13, 7:00 a.m. End: August 31, 5:00 p.m.

33RD ST W INTERSECTION CLOSED AT KENSINGTON RD/NEAULT RD/ELK POINT RD
(water main installation)
Start: August 28, 7:00 a.m. End: September 3, 4:00 p.m.

COLLEGE DR SPEED REDUCTION FROM CENTRAL AVE TO CIRCLE DR E
(ditch excavation)
Start: July 26, 9:00 a.m. End: September 14, 6:00 p.m.

CIRCLE DR E SB CURB & CENTRE LANES CLOSED AT 8TH ST E
(water main maintenance)
Start: July 30, 9:00 a.m. End: September 15, 5:00 p.m.

115TH ST E EB & WB CLOSED FROM BRADWELL AVE TO SPRUCE DR
(water main replacement)
Start: August 26, 8:00 a.m. End: September 22, 4:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

NEAULT RD NB & SB SPEED REDUCTION FROM 33RD ST W & KENSINGTON GATE W
(water main installation)
Start: August 15, 7:00 a.m. END: October 15, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.

Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.