NEW

MCKERCHER DR NB CURB AND MEDIAN LANES CLOSED FROM HERITAGE CRES TO HOLLAND RD
(roadway patching)
NB traffic squeezed into parking lane
Start: July 31, 8:00 a.m. End: July 31, 5:00 p.m.

IDYLWYLD DR N NB CURB LANE CLOSED BETWEEN RUTH ST E TO TAYLOR ST E
(streetlight repairs)
Start: July 31, 9:00 a.m. End: July 31, 3:00 p.m.

PRESTON AVE S SB LANES CLOSED FROM TAYLOR ST E TO ADELAIDE ST E
(roadway patching)
Start: July 31, 9:00 a.m. End: July 31, 5:00 p.m.

ONGOING

IDYLWYLD DR N NB CURB LANE CLOSED FROM IDYLWYLD SERVICE RD TO 60TH ST E
(guardrail repairs)
Start: July 30, 9:00 a.m. End: July 31, 3:00 p.m.

​WANUSKEWIN RD NB CURB LANE CLOSED FROM ARTHUR ROSE AVE TO MARQUIS DR E
(road construction)
Start: July 11, 5:00 a.m. End: August 1, 10:00 p.m.

CIRCLE DR W NB CURB LANE CLOSED AT 33RD ST W
(bridge deck repairs)
Start: July 3, 5:00 a.m. End: August 3, 9:00 p.m.

AVE C N ROAD CLOSED FROM 36TH ST W TO 37TH ST W
(concrete installation & sewer line replacement)
Start: July 25, 9:00 a.m. End: August 8, 7:00 p.m.

COLLEGE DR SPEED REDUCTION FROM CENTRAL AVE TO CIRCLE DR E
(ditch excavation)
Start: July 26, 9:00 a.m. End: August 10, 6:00 p.m.

PRESTON AVE S SB CURB LANE CLOSED FROM COLLEGE DR TO FIELD HOUSE RD
(road construction)
Start: July 17, 7:00 a.m. End: August 10, 7:00 p.m.

IDYLWYLD DR S NB & SB MEDIAN LANES CLOSED BETWEEN SID BUCKWOLD BRIDGE AND 8TH ST E
(pedestrian bridge repairs)
Start: July 30, 9:00 a.m. End: August 16, 7:00 p.m.

CIRCLE DR W NB MEDIAN LANES CLOSED FROM AT 33RD ST W
(overpass rehab)
Start: July 24, 5:00 a.m. End: August 24, 3:00 p.m.

CIRCLE DR E SB CURB & CENTER LANES CLOSED AT 8TH ST E
(water main maintenance)
Start: July 30, 9:00 a.m. End: September 14, 5:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.