You are here

Daily Road Report, July 5

For immediate release: July 4, 2018 - 3:00pm
TU18-414

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.

NEW

IDYLWYLD DR S EB CURB LANE CLOSED FROM LORNE AVE TO CIRCLE DR S
(catch basin repairs)
Start: July 5, 8:00 a.m. End: July 5, 4:00 p.m.

TAYLOR ST E INTERSECTION CLOSED AT MCKINNON AVE S
(water & sewer connection replacement)
Start: July 5, 9:00 a.m. End: July 6, 4:00 p.m.

PRESTON AVE S NB MEDIAN LANE CLOSED AT ARLINGTON AVE
(directional boring)
Start: July 5, 9:00 a.m. End: July 6, 4:00 p.m.

IDYLWYLD DR N NB CURB LANE CLOSED FROM ABERDEEN PL TO 36TH ST E
(resurfacing)
Start: July 5, 10:00 a.m. End: July 6, 6:00 p.m.

IDYLWYLD DR S NB CURB LANE CLOSED AT NIDEROST ST
(catch basin repair)
Start: July 5, 10:30 a.m. End: July 5, 3:30 p.m.

NIGHTWORK

TAYLOR ST E WB MEDIAN LANE CLOSED AT CUMBERLAND AVE S
(Sewer inspection)
Start: July 5, 8:00 p.m. End: July 6, 2:00 a.m.

ONGOING

25TH ST E EB MEDIAN LANE CLOSED AT 1ST AVE N
(Sewer inspection)
Start: July 4, 10:00 p.m. End: July 5, 2:00 a.m.

CIRCLE DR E NB CURB LANE CLOSED FROM 108TH ST TO ATTRIDGE DR
(bridge repairs)
Closure will be set between 9:00 and 3:00 daily.
Start: July 4, 9:00 a.m. End: July 6, 3:00 p.m.

22ND ST W WB ROAD CLOSED FROM AVE K N TO AVE M N
(W&S repairs)
Two-way traffic will be accommodated in the EB lanes.
Start: July 4, 9:00 a.m. End: July 6, 5:00 p.m.

22ND ST E EB CURB LANE CLOSED FROM AVE H S TO AVE B S
(sidewalk & curb replacement)
Start: June 25, 9:00 a.m. End: July 6, 7:00 p.m.

8TH ST E EB CURB LANE CLOSED AT ARLINGTON AVE
(curb expansion)
Start: July 3, 9:00 a.m. End: July 7, 5:00 p.m.

PRESTON AVE N ROAD CLOSED FROM 14TH ST E TO COLLEGE DR
(water/sewer connection tie-in)
Start: June 25, 9:00 a.m. End: July 9, 6:00 p.m.

COLLEGE DR WB CURB LANE CLOSED FROM CUMBERLAND AVE N TO CLARENCE AVE N
(Sidewalk replacement)
Closure set daily 10:00 - 17:00
Start: July 3, 10:00 a.m. End: July 12, 5:00 p.m.

BOYCHUK DR NB PARKING LANE CLOSED FROM 8TH ST E TO ARNASON CRES
(sidewalk repairs)
Start: June 28, 7:00 a.m. End: July 13, 5:00 p.m.

33RD ST E EB CURB LANE CLOSED FROM ONTARIO AVE TO QUEBEC AVE
(concrete replacement)
Start: July 2, 7:00 a.m. End: July 29, 5:00 p.m.

CIRCLE DR W NB CURB LANE CLOSED AT 33RD ST W
(bridge deck repairs)
Start: July 3, 5:00 a.m. End: August 3, 9:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.

Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.