You are here

Daily Road Report, July 5, 2019

For immediate release: July 4, 2019 - 3:00pm
TC19-534

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
 
NEW
 
22ND ST E WB LANES CLOSED AND EB LEFT TURN LANE CLOSED FROM 2ND AVE N TO 3RD AVE N
(Material craning)
Start: July 5, 5:00 a.m. End: July 5, 9:00 a.m.
 
DIEFENBAKER DR WB CURB LANE CLOSED AT PEARSON PL
(Gas line repair)
Start: July 5, 8:00 a.m. End: July 5, 4:00 p.m.
 
33RD ST E WB LANES CLOSED FROM 1ST AVE N TO QUEBEC AVE
(Roadway patching)
2-way traffic maintained in EB lanes
Start: July 5, 9:00 a.m. End: July 5, 5:00 p.m.
 
COLLEGE DR WB LANES SPEED REDUCTION FROM MCORMOND DR TO MCKERCHER DR
(Construction)
Start: July 5, 9:00 a.m. End: November 30, 5:00 p.m.
 
ONGOING
 
CLARENCE AVE S NB & SB CLOSED FROM HILLIARD ST E TO ISABELLA ST E
(Water & sewer work)
Start: July 4, 8:00 a.m. End: July 5, 4:00 p.m.

3RD AVE N NB CURB LANE CLOSED AT DUCHESS ST
(Water main replacement)
Start: June 24, 9:00 a.m. End: July 15, 5:00 p.m.
 
HIGHWAY 16 EB CURB LANE CLOSED AT BOYCHUK DR
(Waste removal)
Start: June 26, 7:00 a.m. End: July 5, 5:00 p.m.
 
BOYCHUK DR SB CURB LANE CLOSED AT KINGSMERE BLVD
(Concrete replacement)
Start: July 3, 9:00 a.m. End: July 7, 5:00 p.m.
 
AVE C N NB PARKING LANE CLOSED FROM 40TH A ST E TO 41ST ST E
(Seeding)
Start: July 2, 7:00 a.m. End: July 9, 5:00 p.m.
 
WANUSKEWIN RD SB LANES CLOSED AT 71ST ST E
(Road construction)
2-way traffic maintained in NB lanes
Start: May 27, 9:00 a.m. End: July 23, 5:00 p.m.
 
BOYCHUK DR RESTRICTIONS REMOVED AT HIGHWAY 16
(Interchange construction)
Temporary intersection on overpass still in use for all directions; 2 way traffic on NB side of structure.
Start: September 30, 12:00 a.m. End: July 31, 4:00 p.m.

MCORMOND DR SINGLE LANE NB & SB FROM KERR RD TO HIGHWAY 5
(Interchange construction)
Start: November 14, 8:00 a.m. End: July 31, 5:00 p.m.

7TH AVE N ROAD CLOSED FROM QUEEN ST TO DUCHESS ST
(Water main replacement)
Start: July 2, 7:00 a.m. End: September 2, 5:00 p.m.

SID BUCKWOLD BRIDGE NB & SB LANES RESTRICTED
(Bridge upgrades)
Lanes restricted in both directions; NB lanes zipper merge near 8th St. SB single lane starting at 20th St.
Start: April 14, 8:30 a.m. End: October 31, 5:00 p.m.

AVE H S INTERSECTION CLOSED AT 11TH ST W
(Construction)
Start: March 11, 7:00 a.m. End: August 31, 5:00 p.m.
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.