NEW
 
VICTORIA AVE NB & SB MEDIAN LANES CLOSED AT 6TH ST E
(Sewer lining)
Start: July 8, 7:00 a.m. End: July 8, 4:00 p.m.
 
CLARENCE AVE S SB CURB LANE CLOSED FROM 8TH ST E TO 6TH ST E
(Sewer lining)
Start: July 8, 7:00 a.m. End: July 8, 4:00 p.m.
 
CUMBERLAND AVE S INTERSECTION CLOSED AT 14TH ST E
(Water main rehabilitation)
Start: July 8, 7:00 a.m. End: August 9, 5:00 p.m.

BOYCHUK DR SB LANES CLOSED FROM HERITAGE CRES TO TAYLOR ST E
(Resurfacing)
Start: July 8, 9:00 a.m. End: July 10, 5:00 p.m.
 
BOYCHUK DR SB CURB LANE CLOSED AT NEMEIBEN RD
(Concrete replacement)
Start: July 8, 9:00 a.m. End: July 12, 5:00 p.m.
 
TAYLOR ST E EB AND WB CURB LANES CLOSED FROM BRUDELL RD TO BOYCHUK DR
(Concrete work)
Start: July 8, 9:00 a.m. End: July 16, 5:00 p.m.

ONGOING
 
3RD AVE N NB CURB LANE CLOSED AT DUCHESS ST
(Water main replacement)
Start: June 24, 9:00 a.m. End: July 15, 5:00 p.m.

HIGHWAY 16 EB MEDIAN LANE CLOSED AT BOYCHUK DR
(Waste removal from median)
Start: July 5, 8:00 a.m. End: July 9, 4:00 p.m.
 
AVE C N NB PARKING LANE CLOSED FROM 40TH A ST E TO 41ST ST E
(Seeding)
Start: July 2, 7:00 a.m. End: July 9, 5:00 p.m.
 
WANUSKEWIN RD SB LANES CLOSED AT 71ST ST E
(Road construction)
2-way traffic maintained in NB lanes
Start: May 27, 9:00 a.m. End: July 23, 5:00 p.m.
 
BOYCHUK DR RESTRICTIONS REMOVED AT HIGHWAY 16
(Interchange construction)
Temporary intersection on overpass still in use for all directions; 2 way traffic on NB side of structure.
Start: September 30, 12:00 a.m. End: July 31, 4:00 p.m.

MCORMOND DR SINGLE LANE NB & SB FROM KERR RD TO HIGHWAY 5
(Interchange construction)
Start: November 14, 8:00 a.m. End: July 31, 5:00 p.m.

7TH AVE N ROAD CLOSED FROM QUEEN ST TO DUCHESS ST
(Water main replacement)
Start: July 2, 7:00 a.m. End: September 2, 5:00 p.m.

SID BUCKWOLD BRIDGE NB & SB LANES RESTRICTED
(Bridge upgrades)
Lanes restricted in both directions; NB lanes zipper merge near 8th St. SB single lane starting at 20th St.
Start: April 14, 8:30 a.m. End: October 31, 5:00 p.m.

COLLEGE DR WB SPEED REDUCTION FROM MCORMOND DR TO MCKERCHER DR
(Construction)
Start: July 5, 9:00 a.m. End: November 30, 5:00 p.m.
 
AVE H S INTERSECTION CLOSED AT 11TH ST W
(Construction)
Start: March 11, 7:00 a.m. End: August 31, 5:00 p.m.
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.