NEW

22ND ST W EB CURB LANE CLOSED AT AVE O S
(Roadway patching)
Start: June 27, 7:00 a.m. End: June 27, 5:00 p.m.

25TH ST E WB MEDIAN LANE CLOSED FROM 1ST AVE N TO IDYLWYLD DR N
(Median be maintenance)
Start: June 27, 9:00 a.m. End: June 27, 11:00 a.m.

8TH ST E EB CURB LANE CLOSED FROM CAIRNS AVE TO WIGGINS AVE S
(Sidewalk repair)
Start: June 27, 9:00 a.m. End: June 27, 1:00 p.m.

CIRCLE DR E NB MEDIAN LANE CLOSED AT TAYLOR ST E
(wall pack light repairs)
Start: June 27, 9:00 a.m. End: June 27, 3:00 p.m.

RUTH ST E EB PARKING LANE CLOSED THROUGH THE INTERSECTIONS FROM WILSON CRES TO ROYAL AVE
(sewer lining)
Start: June 27, 11:00 a.m. End: June 27, 7:00 p.m.

IDYLWYLD DR S NB MEDIAN LANE SECTION CLOSED BETWEEN 8TH ST E AND SID BUCKWOLD BRIDGE
(guardrail repair)
Start: June 27, 12:00 p.m. End: June 27, 12:00 p.m.

IDYLWYLD DR S NB & SB MEDIAN LANES CLOSED NORTH OF LORNE AVE EXIT
(concrete repair)
Closure will be set between 9:00 & 3:00 p.m. daily.
Start: June 27, 9:00 a.m. End: June 28, 3:00 p.m.

33RD ST W EB & WB CURB LANES CLOSED FROM AVE C N TO AVE D N
(directional boring)
Start: June 27, 7:00 a.m. End: June 29, 5:00 p.m.

NIGHTWORK
CIRCLE DR E NB RAMPS AND CURB LANE CLOSED AT 8TH ST E
(roadway resurfacing)
Start: June 27, 7:00 p.m. End: June 29, 6:00 a.m.

CIRCLE DR E SB RAMPS & CURB LANE CLOSED AT TAYLOR ST E
(road resurfacing)
Start: June 25, 7:00 p.m. End: June 27, 6:00 a.m.

ONGOING

PRESTON AVE S NB PARKING LANE CLOSED FROM WILSON CRES TO LOUISE AVE
(concrete replacement)
Start: June 15, 7:00 a.m. End: June 27, 6:00 p.m.

VICTORIA AVE NB CLOSED FROM MAIN ST TO 10TH ST E
(roadwork)
Start: June 18, 7:00 a.m. End: July 1, 4:00 p.m.

22ND ST E EB CURB LANE CLOSED FROM AVE H S TO AVE B S
(sidewalk & curb replacement)
Start: June 25, 9:00 a.m. End: July 6, 7:00 p.m.

PRESTON AVE N ROAD CLOSED FROM 14TH ST E TO COLLEGE DR
(water/sewer connection tie-in)
Start: June 25, 9:00 a.m. End: July 9, 6:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.

Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.