NEW

8TH ST E EB LEFT TURN BAY CLOSED AT CLARENCE AVE S
(Radio installation)
Start: May 11, 9:00 a.m. End: May 11, 1:00 p.m.

NIGHTWORK

CIRCLE DRIVE SPEED REDUCTIONS - ROTATING LOCATIONS
(Street Sweeping Train)
Sweeping will not take place on weekends (Friday/Saturday).
Start: May 7, 8:00 p.m. End: June 8, 6:00 a.m.

3RD AVE S ROAD CLOSED FROM 19TH ST E TO SPADINA CRES E
(crane work)
Start: May 9, 12:00 a.m. End: May 10, 12:00 a.m.

ONGOING

1ST AVE N SB PARKING LANE CLOSED FROM 26TH ST E TO 25TH ST E
(sidewalk replacement)
Start: May 8, 7:00 a.m. End: May 14, 5:00 p.m.

HIGHWAY 5 WB ROAD CLOSED AT MCORMOND DR
(construction)
Two-way traffic will be accommodated in the EB lanes.
Start: May 10, 5:00 a.m. End: May 14, 8:00 p.m.

33RD ST W WB CURB LANE CLOSED FROM AVE K N TO VALENS DR
(sidewalk replacement)
Start: May 9, 11:00 a.m. End: May 15, 5:00 p.m.

33RD ST W EB & WB CURB LANES CLOSED AT AVE D N
(intersection improvements)
Start: May 10, 11:00 a.m. End: May 19, 1:00 p.m.

HIGHWAY 16 EB LANES CLOSED AT BOYCHUK DR
(girder installation)
Two-way traffic will be accommodated in WB lanes.
Start: May 6, 6:00 a.m. End: May 19, 4:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.

Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.