NEW
TAYLOR ST W INTERSECTION CLOSED AT COY AVE
(Water main repair)
Start: November 21, 8:00 a.m. End: November 21, 5:00 p.m.
8TH ST E EB CURB LANE CLOSED AT EMERSON AVE
(Traffic signal work)
Start: November 21, 9:00 a.m. End: November 21, 3:00 p.m.
4TH AVE S ROAD CLOSED FROM 20TH ST E TO 21ST ST E
(Vault repairs & crane lift)
Start: November 21, 9:00 a.m. End: November 21, 3:00 p.m.
1ST AVE S EB & SB CURB LANE CLOSED AT 20TH ST E
(Catch basin repair)
Start: November 21, 9:30 a.m. End: November 21, 12:30 p.m.
ONGOING
BALTZAN BLVD SIDEWALK CLOSED AT MCORMOND DR
(Construction)
Start: November 14, 8:00 a.m. End: November 25, 5:00 p.m.
4TH AVE S NB CURB & PARKING LANES CLOSED FROM 20TH ST E TO 21ST ST E
(Vault work)
Start: October 7, 7:00 p.m. End: December 31, 4:30 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.