NEW

TAYLOR ST E VARIOUS PARKING LANES CLOSED FROM CLARENCE AVE N TO MCKINNON AVE S
(Well monitoring)
Start: October 26, 7:00 a.m. End: October 26, 4:00 p.m.

CUMBERLAND AVE S SB LANES CLOSED FROM ADELAIDE ST E TO RUTH ST E
(Sanitary sewer lining)
Start: October 26, 7:00 a.m. End: October 26, 5:00 p.m.

CUMBERLAND AVE S INTERSECTION CLOSED AT HILLIARD ST E
(Hydrant replacement)
Start: October 26, 8:00 a.m. End: October 27, 5:00 p.m.

RUTH ST E ROAD CLOSED FROM UNDERWOOD AVE TO VICTORIA AVE
(Water main repair)
Start: October 26, 8:00 a.m. End: October 29, 4:00 p.m.

CIRCLE DR E NB LANES SQUEEZE OVER AT ATTRIDGE DR
(Construction)
Start: October 26, 9:00 a.m. End: October 29, 3:00 p.m.

ATTRIDGE DR WB LANES SQUEEZE OVER FROM ATTRIDGE DR TO CIRCLE DR E
(Manhole access)
Start: October 26, 9:00 a.m. End: October 29, 3:00 p.m.

ONGOING

8TH ST E ROAD CLOSED FROM RANGE ROAD 3044 TO MCORMOND DR
(Trucking route)
Start: February 24, 7:00 a.m. End: October 26, 5:00 p.m.

3RD AVE N NB CURB LANE CLOSED AT DUKE ST
(Water main inspections)
Start: October 23, 8:30 a.m. End: October 29, 4:00 p.m.

3RD AVE N NB PARKING LANE CLOSED AT PRINCESS ST
(Water main inspection)
Start: October 23, 8:30 a.m. End: October 29, 4:00 p.m.

1ST AVE N NB LANES CLOSED FROM QUEEN ST TO KING ST
(Water main inspection)
Start: October 23, 9:00 a.m. End: October 29, 5:00 p.m.

SPADINA CRES W NB LANES CLOSED FROM DUDLEY ST TO 11TH ST W
(Water main construction)
NB traffic yields to SB traffic
Start: September 23, 8:00 a.m. End: October 30, 4:00 p.m.

1ST AVE N NB MEDIAN & LEFT TURN LANE CLOSED AT 25TH ST E
(Water main inspection)
Start: October 23, 9:00 a.m. End: October 30, 5:00 p.m.

FEDORUK DR WB ROAD CLOSED FROM KONIHOWSKI RD TO CENTRAL AVE
(Roadway twinning)
Start: September 30, 8:00 a.m. End: October 30, 5:00 p.m.

1ST AVE N NB MEDIAN LANE CLOSED; SB MEDIAN & LEFT TURN LANE CLOSED FROM 22ND ST E TO 23RD ST E
(Water main inspection)
Start: October 1, 8:00 a.m. End: October 31, 5:00 p.m.

SPADINA CRES W ROAD CLOSED FROM SCHUYLER ST TO POWER RD
(Construction)
Start: September 14, 7:00 a.m. End: November 2, 5:00 p.m.

MCORMOND DR NB CURB LANE CLOSED FROM STENSRUD RD TO BALTZAN BLVD
(Water main work)
Start: September 23, 8:00 a.m. End: November 3, 5:00 p.m.
 

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.

For more information about current road restrictions and construction, visit saskatoon.ca/construction.