NEW

8TH ST E EB CURB LANE CLOSED FROM GROSVENOR AVE TO MCCOOL AVE
(curb & gutter installation)
Start: September 21, 8:00 a.m. End: September 25, 5:00 p.m.

ATTRIDGE DR EB & WB MEDIAN LANES CLOSED AT CIRCLE DR E
(minor bridge repairs)
Start: September 21, 9:00 a.m. End: September 21, 3:00 p.m.

NIGHTWORK

IDYLWYLD DR S NB CURB LANE CLOSED BETWEEN CIRCLE DR S AND ADELAIDE ST E
(pavement markings)
Start: September 21, 7:00 p.m. End: September 22, 7:00 a.m.

ONGOING

22ND ST W EB & WB MEDIAN & CENTRE LANES CLOSED FROM AVE U S TO AVE V S
(water connection repair)
Start: September 20, 9:00 a.m. End: September 21, 3:00 p.m.

QUEBEC AVE ROAD CLOSED FROM 34TH ST E TO 36TH ST E
(hydrant repair)
Start: September 12, 7:00 a.m. End: September 22, 4:00 p.m.

22ND ST W WB CURB LANE CLOSED FROM AVE L N TO AVE P N
(sidewalk replacement)
Start: September 17, 9:00 a.m. End: September 26, 5:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

115TH ST E ROAD CLOSED FROM SPRUCE DR TO BRADWELL AVE
(water main rehab)
Start: September 18, 7:30 a.m. End: October 8, 4:00 p.m.

115TH ST E ALL DIRECTIONS CLOSED FROM DUNLOP ST TO SPRUCE DR
(water main rehab)
Start: September 18, 7:30 a.m. End: October 8, 4:00 p.m.

NEAULT RD NB & SB SPEED REDUCTION FROM 33RD ST W & KENSINGTON GATE W
(water main installation)
Start: August 15, 7:00 a.m. END: October 15, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.