NEW

BROADWAY AVE SB LANES CLOSED FROM 10TH ST TO MAIN ST
(Crane lift)
Start: July 24, 6:00 a.m. End: July 25, 5:00 p.m.

IDYLWYLD DR N SB CURB LANE CLOSED FROM 31ST ST W TO 30TH ST W
(Road reconstruction)
Start: July 24, 7:00 a.m. End: July 24, 3:00 p.m.

IDYLWYLD DR N SB CURB LANE CLOSED FROM 41ST ST W TO 40TH A ST W
(Catch basin repairs)
Start: July 24, 8:00 a.m. End: July 25, 4:00 p.m.

CIRCLE DR S SB CURB & CENTRE LANES CLOSED FROM 11TH ST W TO VALLEY RD
(Roadway patching)
Start: July 25, 7:00 a.m. End: July 25, 1:00 p.m.

CIRCLE DR S SB CURB LANE & NEXT LANE CLOSED FROM SPADINA CRES W TO ST HENRY AVE
(Roadway patching)
Start: July 25, 7:00 a.m. End: July 25, 1:00 p.m.

 

NIGHTWORK

CIRCLE DR E NB & SB MEDIAN LANES CLOSED AT 8TH ST E
(Deck rehab)
Start: July 11, 7:00 p.m. End: July 25, 7:00 p.m.

CIRCLE DR E NB & SB CURB LANES CLOSED AT 8TH ST E
(Deck rehab)
Start: July 22, 7:00 p.m. End: August 13, 5:00 p.m.

CIRCLE DR E NB CURB LANE CLOSED AT COLLEGE DR
(Guardrail repair)
Start: July 22, 7:00 p.m. End: August 13, 7:00 p.m.

 

ONGOING

20TH ST W EB CURB LANE CLOSED FROM AVE L S TO AVE K S
(Sidewalk Replacement)
Start: July 23, 7:00 a.m. End: July 24, 5:00 p.m.

4TH AVE N INTERSECTION CLOSED AT 23RD ST E
(Food Truck Wars)
Start: July 21, 7:00 a.m. End: July 25, 11:00 a.m.

RUTH ST E ROAD CLOSED FROM VICTORIA AVE TO BROADWAY AVE
(Water main repairs)
Start: July 13, 7:00 a.m. End: July 25, 4:00 p.m.

RUTH ST E EB PARKING LANE CLOSED FROM CLARENCE AVE S TO MCKINNON AVE S
(Sidewalk replacement)
Start: July 19, 7:00 a.m. End: July 25, 5:00 p.m.

20TH ST W WB CURB & PARKING LANE CLOSED FROM AVE K S TO AVE M S
(Sidewalk replacement)
Start: July 19, 9:00 a.m. End: July 25, 5:00 p.m.

BROADWAY AVE SB CURB LANE CLOSED FROM 5TH ST E TO 2ND ST E
(Catch basin repair)
Start: July 20, 7:00 a.m. End: July 25, 5:00 p.m.

BROADWAY AVE SB PARKING LANE CLOSED AT 6TH ST E
(Concrete work)
Start: July 20, 9:00 a.m. End: July 25, 5:00 p.m.

RUTH ST E ROAD CLOSED FROM VICTORIA AVE TO MELROSE AVE
(Water main repairs)
Start: July 12, 7:00 a.m. End: July 25, 6:00 p.m.

8TH ST E INTERSECTION CLOSED AT NEW MCORMOND DR
(Construction)
Start: April 26, 7:00 a.m. End: July 26, 5:00 p.m.

BROADWAY AVE SB PARKING LANE CLOSED AT 70TH ST E
(Concrete work)
Start: July 20, 9:00 a.m. End: July 27, 5:00 p.m.

FEDORUK DR EB & WB CURB LANES CLOSED AT KONIHOWSKI RD
(Construction)
Start: July 14, 7:00 a.m. End: July 27, 5:00 p.m.

RUTH ST E ROAD CLOSED FROM LORNE AVE TO VERNON AVE
(Water main lining)
Start: July 22, 7:00 a.m. End: July 28, 5:00 p.m.

TAYLOR ST E INTERSECTION CLOSED AT DUFFERIN AVE
(Stormwater pond work)
Start: June 7, 7:00 a.m. End: July 31, 5:00 p.m.