You are here

Weekend Road Report, July 7-8

For immediate release: July 6, 2018 - 3:33pm
TU18-417

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.

NEW

1ST AVE N ROAD CLOSED FROM 26TH ST E TO QUEEN ST
(crane lift)
Start: July 7, 5:30 a.m. End: July 8, 4:00 p.m.

SB ROAD CLOSED ON IDYLWYLD DR S AT 8TH ST EXIT RAMP
(roadway patching)
All SB traffic must use 8th St exit ramp.
Start: July 8, 6:00 a.m. End: July 8, 10:00 a.m.

CLARENCE AVE S NB CURB LANE CLOSED FROM 14TH ST E TO 15TH ST E
(sewer lining)
Start: July 7, 7:00 a.m. End: July 7, 5:00 p.m.

PRESTON AVE S NB LANES CLOSED FROM CIRCLE DRIVE TO ARLINGTON AVE AND SB LANES CLOSED FROM JARVIS DR TO WILSON CRES
(Resurfacing)
Start: July 7, 7:00 a.m. End: July 8, 12:00 p.m.

IDYLWYLD DR N NB ROAD CLOSED FROM 31ST ST E TO 37TH ST E
(resurfacing)
Two-way traffic will be accommodated in the SB lanes. No access to Idylwyld Dr from 33rd St WB. 33rd St EB must proceed NB or SB on Idylwyld Dr.
Start: July 7, 7:00 a.m. End: July 8, 5:00 p.m.

CLARENCE AVE N NB & SB MEDIAN LANES CLOSED FROM COLLEGE DR TO UNIVERSITY DR
(sanitary lining)
Start: July 7, 8:00 a.m. End: July 7, 7:00 p.m.

AVE H N INTERSECTION CLOSED AT 29TH ST W
(water main replacement)
Start: July 7, 9:00 a.m. End: July 21, 5:00 p.m.

IDYLWYLD DR S SB ROAD CLOSED FROM 4TH ST W TO HILLIARD ST W
(roadway patching)
Two-way traffic will be accommodated in the NB lanes.
Start: July 8, 10:00 a.m. End: July 8, 5:00 p.m.​

ONGOING

8TH ST E EB CURB LANE CLOSED AT ARLINGTON AVE
(curb expansion)
Start: July 3, 9:00 a.m. End: July 7, 5:00 p.m.

PRESTON AVE N ROAD CLOSED FROM 14TH ST E TO COLLEGE DR
(water/sewer connection tie-in)
Start: June 25, 9:00 a.m. End: July 9, 6:00 p.m.

COLLEGE DR WB CURB LANE CLOSED FROM CUMBERLAND AVE N TO CLARENCE AVE N
(Sidewalk replacement)
Closure set daily 10:00 - 5:00
Start: July 3, 10:00 a.m. End: July 12, 5:00 p.m.

BOYCHUK DR NB PARKING LANE CLOSED FROM 8TH ST E TO ARNASON CRES
(sidewalk repairs)
Start: June 28, 7:00 a.m. End: July 13, 3:00 p.m.

33RD ST E EB CURB LANE CLOSED FROM ONTARIO AVE TO QUEBEC AVE
(concrete replacement)
Start: July 2, 7:00 a.m. End: July 29, 5:00 p.m.

CIRCLE DR W NB CURB LANE CLOSED AT 33RD ST W
(bridge deck repairs)
Start: July 3, 5:00 a.m. End: August 3, 9:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.

Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.