NEW

No new projects are scheduled to start on this date.

ONGOING

TAYLOR ST E EB & WB LANES RESTRICTIONS FROM MCKERCHER DR TO HERITAGE CRES
(Concrete repairs)
Start: May 10, 9:00 a.m. End: May 23, 6:00 p.m.

33RD ST E EB CURB LANE CLOSED FROM QUEBEC AVE TO WARMAN RD
(Sidewalk replacement)
Start: May 21, 7:00 a.m. End: June 10, 5:00 p.m.

LORNE AVE NB & SB MEDIAN LANES CLOSED AT CIRCLE DR W
(Concrete work)
Start: May 11, 7:00 a.m. End: June 15, 5:00 p.m.

MCORMOND DR ROAD CLOSED AT BRIGHTON COMMON
(Vault work)
Start: April 27, 8:00 a.m. End: June 30, 4:00 p.m.

8TH ST E ROAD CLOSED FROM RANGE ROAD 3044 TO MCORMOND DR
(Trucking route)
Start: February 24, 7:00 a.m. End: October 26, 5:00 p.m.

IDYLWYLD DR S NB ROAD CLOSED FROM 8TH ST E TO 20TH ST E
(Bridge rehabilitation)
Start: April 5, 7:00 a.m. End: October 30, 5:00 p.m.

All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances. Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers. For COVID-19 impacts to bridge walkways, pedestrian overpasses and underpasses, please visit saskatoon.ca/COVID-19.