NEW

IDYLWYLD DR N SB MEDIAN LANE CLOSED FROM 33RD ST W TO 32ND ST W
(traffic pole repairs)
Start: September 9, 6:00 a.m. End: September 9, 11:00 a.m.

LORNE AVE NB MEDIAN LANES CLOSED FROM 8TH ST E TO 9TH ST E
(road repair)
Start: September 8, 7:00 a.m. End: September 8, 5:00 p.m.

COLLEGE DR EB CURB LANE FROM SPADINA CRES E TO SASKATCHEWAN CRES
(expansion joint repairs)
Start: September 8, 7:00 a.m. End: September 8, 5:30 p.m.

IDYLWYLD DR S NB & SB MEDIAN LANES CLOSED AT SAUNDERS PL
(guardrail repair)
Start: September 9, 9:00 a.m. End: September 9, 3:00 p.m.

IDYLWYLD DR S NB MEDIAN AND CENTRE LANES CLOSED FROM AUDITORIUM AVE TO 22ND ST E
(manhole repairs)
Start: September 9, 10:00 a.m. End: September 9, 12:30 p.m.

IDYLWYLD DR S NB CURB LANE CLOSED AT AUDITORIUM AVE
(manhole repairs)
Start: September 9, 12:30 p.m. End: September 9, 4:00 p.m.

NIGHTWORK

IDYLWYLD DR S NB MEDIAN LANE CLOSED FROM CASCADE ST TO TAYLOR ST E
(road resurfacing)
Start: September 8, 7:00 p.m. End: September 10, 7:00 a.m.

IDYLWYLD DR S NB CURB LANE CLOSED FROM KELVIN AVE TO TAYLOR ST E
(roadway resurfacing)
Start: September 7, 7:00 p.m. End: September 8, 7:00 a.m.

ONGOING

CENTRAL AVE NB PARKING LANE CLOSED FROM 103RD ST E TO CENTRAL PL
(flow monitoring)
Start: September 4, 8:00 a.m. End: September 8, 6:00 p.m.

PRESTON AVE S SB CURB LANE CLOSED FROM COLLEGE DR TO FIELD HOUSE RD
(road construction)
Start: July 17, 7:00 a.m. End: September 9, 7:00 p.m.

TAYLOR ST E EB CURB LANE CLOSED FROM ARLINGTON AVE TO CIRCLE DR E
(intersection improvements)
Start: September 5, 9:00 a.m. End: September 10, 5:00 p.m.

QUEBEC AVE ROAD CLOSED FROM 36TH ST E TO 38TH ST E
(hydrant replacements)
Start: September 6, 7:00 a.m. End: September 11, 5:00 p.m.

NEAULT RD NB LANES CLOSED AT 33RD ST W
(primary water main construction)
Two-way traffic will be accommodated in the SB lanes.
Start: September 6, 9:00 a.m. End: September 12, 4:00 p.m.

COLLEGE DR SPEED REDUCTION FROM CENTRAL AVE TO CIRCLE DR E
(ditch excavation)
Start: July 26, 9:00 a.m. End: September 14, 6:00 p.m.

CIRCLE DR E SB CURB & CENTRE LANES CLOSED AT 8TH ST E
(water main maintenance)
Start: July 30, 9:00 a.m. End: September 15, 5:00 p.m.

115TH ST E ROAD CLOSED FROM BRADWELL AVE TO SPRUCE DR
(water main replacement)
Start: August 26, 8:00 a.m. End: September 22, 4:00 p.m.

115TH ST E ROAD CLOSED FROM SPRUCE DR TO FOREST DR
(water main rehab)
Start: September 4, 12:00 p.m. End: October 1, 4:00 p.m.

CENTRAL AVE SB LANES CLOSED FROM KONIHOWSKI RD TO FEDORUK DR
(roadway construction)
Two-way traffic will be accommodated in the NB lanes.
Start: November 6, 7:00 a.m. End: October 1, 5:00 p.m.

NEAULT RD NB & SB SPEED REDUCTION FROM 33RD ST W & KENSINGTON GATE W
(water main installation)
Start: August 15, 7:00 a.m. END: October 15, 5:00 p.m.