Building Permit Timelines
Permit Timelines
The department is currently meeting service levels for single-family dwellings, two-unit dwellings, row housing, and apartment buildings that fall under Part 9 of the National Building Code. All other building permit timelines are estimated at 5 - 7 business days over the targeted service level.
After you have applied for your permit, the Building Standards team will process your application. The established service level targets outlined below are represented in business days, and includes reviews by all city departments.
New Construction | Alterations | |
---|---|---|
Single-family dwelling | 5-7 | 5 |
Two-unit dwelling | 5-7 | 5 |
Row Housing | 15-20 | 5-8 |
Apartment Buildings | 17-22 | 10-15 |
Commercial, Assembly, Industrial & Institutional | 17-22 | 10-15 |
Demolitions | 5-8 | N/A |