2019 construction and road maintenance update

For immediate release: August 9, 2019 - 10:10am
TC19-609

From major infrastructure rehabilitation to general road maintenance, the 2019 construction season is progressing as planned and on schedule in Saskatoon. City Council invested over $61 million in 2019 to make more of Saskatoon’s streets, bridges and sidewalks, smoother, safer and longer-lasting.

“With so many active projects underway, we know navigating around Saskatoon can be inconvenient,” says Matt Jurkiewicz, Interim Director, Construction & Design. “We plan our short construction season to lessen these impacts as much as possible, but of course it’s not possible to avoid traffic delays altogether. We’re asking everyone to remember the work is necessary and will be worth it in the long run.”

  • The interchanges at Boychuk Drive and Highway 16 and McOrmond Drive and College Drive are complete and open.
     
  • Phase 1 of the Senator Sid Buckwold Bridge rehabilitation project has reached the mid-way point and remains on track for completion in October. In 2020, Phase 2 will require the lanes heading into downtown to be closed.
     
  • Water main/connection replacements will improve water service for 387 properties in City Park (2018-2020) and Riversdale (2019-2020). City Park remains on schedule and Riversdale is ahead of schedule. Completion of the current phases is anticipated in early fall.  
     
  • Other water main replacement locations include 14th Street East and Bates Crescent, Acadia Drive between Leddy Crescent and Harrington Street, and 12th Street East between Broadway Avenue and Eastlake Avenue.
     
  • Completed road improvements: resurfacing of Circle Drive from Millar Avenue to the Circle Drive North Bridge; and sections of Taylor Street, Boychuk Drive and Kenderdine Road. The twinning of Wanuskewin Road north of 71st Street is scheduled for completion in October.
  • Upcoming road construction: resurfacing the westbound lanes on College Drive from the city limits to the Canadian Pacific Rail overpass, resurfacing Idylwyld Drive northbound lanes from 25th Street to 31st Street, and resurfacing Preston Avenue northbound lanes from Taylor Street to 8th Street.
     
  • Road and sidewalk maintenance: spring street sweeping was completed through all neighbourhoods in 7 weeks, back lane grading started in July and runs through to October, and sidewalk, pothole and utility cut repairs occur daily across the entire city.

Along with better project coordination, such as sidewalk and roadway overhauls being done at the same time and continuing construction overnight when possible, the City has also adopted a new purchasing policy that allows for the hiring of the best company for the job based on experience, qualifications and construction plan, not just the lowest bid.

We thank you for your pave-tience during construction. We know it can be a real ‘pain in the asphalt.’