Biosolids Pipeline Corridor Project

The City of Saskatoon’s (City) Wastewater Treatment Plant operates a Biosolids Handling Facility in the Rural Municipality of Corman Park (RMCP), north of Saskatoon. The Biosolids Handling Facility has a series of settling lagoons that play a critical part in the wastewater treatment process. Biosolids generated at the wastewater treatment plant are dewatered at the facility and ultimately, fertilizer is produced for nearby landowners.
Two pipelines run underground from the Wastewater Treatment Plant to the Biosolids Handling Facility. The pipelines, constructed in 1984 and 2005, must be replaced as geometric constraints and poor physical condition have made it impossible to remove the hard substances that form and accumulate on the pipeline walls. The new pipelines will have higher capacities and will be designed to mitigate the blockages that have plagued the existing pipes for many years.
The City has opted to include water and wastewater lines within the pipeline corridor that will provide service to the City of Martensville. These pipes are required for future growth of the community as well as meeting regulatory compliance with the Water Security Agency.
The preferred pipeline route as shown was developed by utilizing existing rights-of-way within the RMCP. The routing was developed with a number of considerations including: environmental impacts, operational and maintenance considerations, resident disruption and future development..
While the timing for impacting specific areas is still undetermined, the general project schedule will entail:
- Spring 2026: Construction Kick-Off
- Fall 2027: Construction Completion
If you have any feedback or questions regarding the project, please contact the project team using the contact information above.
Wanuskewin Road now open as project advances
While Wanuskewin Road will fully reopen to traffic, construction activities related to the project will continue in the area. Drivers may still encounter intermittent lane restrictions, reduced speeds or construction vehicles and are reminded to follow all posted signage and exercise caution while travelling through the area.
2026 Construction Phases
Phase 1: WWTP & Silverwood Dog Park/Meewasin
Complete
Phase 2: Wanuskewin Road (South & North of Marquis Drive)
Complete
Phase 3: Wanuskewin Road (North of Marquis Drive)
Complete. Minor site restorations.
Phase 4: Full Closure of Wanuskewin Road (North of Marquis Drive)
Complete. Minor site restorations and adjacent pipeline work ongoing in the ditches.
Frequently Asked Questions
Why are we doing this?
The existing sludge pipelines have reached the end of their service life. This causes operational problems for the Wastewater Treatment Plant as the pipes require frequent maintenance and are prone to failure.
Why did we pick this alignment/route?
A number of factors were considered in developing the route including environmental impacts, operational and maintenance considerations, resident disruption and future development. The route was also adjusted to avoid areas that will be affected by future Saskatoon Freeway construction. Minimizing the disruption to private property owners in terms of property access during construction was a key consideration in route selection.
Who's paying for this project?
The project is being jointly funded by the City of Saskatoon, City of Martensville and the Federal and Provincial Governments through Investing in Canada Infrastructure Program (ICIP) Funding.
How long will this project take?
Construction will begin in spring 2026 and be completed in the fall of 2027.
What is being constructed, and why?
The City is replacing the pipelines that provide conveyance to and from the Biosolids Handling Facility located north of the City. The existing pipes have reliability and capacity and require replacement. The new pipelines have been designed to meet the future capacity requirements of our growing city.
A Purple Water line is also being constructed in conjunction with SaskWater. Purple Water consists of effluent from the Wastewater Treatment Plant and is beneficial for use in industrial and agricultural operations.
How long will the project take?
Given the extensive amount of pipeline construction involved, the work taking place on Wanuskewin Road will not be completed until October of 2026. The contractor has deployed multiple crews, reducing the overall timeline for the closures.
What is happening near the Silverwood Golf Course and Dog Park?
The pipelines are being installed trenchlessly using Horizontal Directional Drilling (HDD). The pipes are being installed in this manner rather than by open excavation in order to minimize impacts to the users of the Meewasin trail system, golf course, and dog park.
Why must the work near the Silverwood Golf Course and Dog Park be continuous 24/7?
Horizontal Directional Drilling (HDD) requires that drilling be a continuous operation until the pipeline installation is complete. Pausing the drilling operation overnight is not possible as it carries serious risks such as the seizing of the drill head due to soil pressure.
Why was the drill rig set up inside the Wastewater Treatment Plant rather than at the north end of the Silverwood Golf Course?
The drill rig was required to be placed at the south end of the trenchless installation for the following reasons:
- There is limited space and steep terrain at the northern location which is prohibitive for setting up the equipment and would have require significant earth work to establish a working platform.
- The drill rig needs to be placed at the lower end of the pipeline profile to effectively recover excavated materials. Due to the existing topography, the low end of the pipe is located at the south end of the installation.