Daily Road Report, July 5, 2022
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only. 
 
NEW 
 
TAYLOR ST E WB CURB LANE CLOSED FROM CIRCLE DR E TO ARLINGTON AVE 
(Landscaping repair) 
Start: July 5, 7:00 a.m. End: July 5, 12:00 p.m. 
 
CIRCLE DR E EB & WB MEDIAN LANES CLOSED FROM QUEBEC AVE TO VENTURE CRES 
(Concrete replacement) 
Start: July 5, 7:00 a.m. End: July 10, 5:00 p.m. 
 
BROADWAY AVE ROAD CLOSED FROM ISABELLA ST E TO HILLIARD ST E 
(Roadway patching) 
Start: July 5, 9:00 a.m. End: July 5, 3:00 p.m. 
 
CIRCLE DR E NB CURB LANE CLOSED FROM HIGHWAY 16 TO TAYLOR ST E 
(Streetlight repair) 
Start: July 5, 9:30 a.m. End: July 5, 3:30 p.m. 
 
OVERNIGHT 
 
IDYLWYLD DR N NB CURB & SHOULDER CLOSED FROM 51ST ST E TO MARQUIS DR E 
(Road resurfacing) 
Start: July 5, 7:00 p.m. End: July 6, 7:00 a.m. 
 
51ST ST E RAMP CLOSED FROM 51ST ST E TO IDYLWYLD DR N 
(Road resurfacing) 
Start: July 5, 7:00 p.m. End: July 6, 7:00 a.m. 
 
ATTRIDGE DR EB & WB MEDAIN LANES CLOSED FROM CIRCLE DR E TO CIRCLE DR E 
(Overpass rehabilitation) 
Start: July 5, 8:00 p.m. End: July 16, 7:30 p.m. 
 
ONGOING 
 
CIRCLE DR E WB CURB & CENTER LANE CLOSED AT 1ST AVE N 
(Road repair) 
Start: July 4, 7:00 p.m. End: July 5, 6:00 a.m. 
 
3RD AVE N ROAD CLOSED FROM 25TH ST TO QUEEN ST 
(Water main repair) 
Start: June 14, 7:00 a.m. End: July 5, 5:00 p.m. 
 
CLARENCE AVE S INTERSECTION CLOSED AT BUTE ST 
(Construction) 
Start: June 23, 7:00 a.m. End: July 11, 5:00 p.m. 
 
1ST AVE N NB PARKING LANE & SIDEWALK CLOSED FROM 23RD ST E TO 24TH ST E 
(Cable work) 
Start: July 4, 8:00 a.m. End: July 13, 4:30 p.m. 
 
WARMAN RD SB CURB LANE CLOSED AT 33RD ST E 
(Intersection improvements) 
Start: June 23, 7:00 a.m. End: July 14, 5:00 p.m. 
 
33RD ST E WB CURB LANE CLOSED AT WARMAN RD 
(Intersection improvements) 
Start: June 23, 7:00 a.m. End: July 14, 5:00 p.m. 
 
DUNDONALD AVE SB CURB LANE CLOSED FROM 11TH ST W TO CAEN ST 
(Drainage improvements) 
Start: June 28, 7:00 a.m. End: July 25, 4:30 p.m. 
 
MCORMOND DR ROAD CLOSED AT BRIGHTON BLVD 
(New road construction) 
Start: June 29, 7:00 a.m. End: August 8, 5:00 p.m. 
 
RUTH ST E INTERSECTION CLOSED AT CAIRNS AVE 
(Water main replacement) 
Start: June 29, 7:00 a.m. End: August 22, 5:00 p.m. 
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances. 