Daily Road Report - June 15
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
DIEFENBAKER DR CLOSED FROM DOUGLAS CRES TO CENTENNIAL DR
(Road resurfacing)
Start: June 15, 7:00 a.m. End: June 16, 5:00 p.m.
20TH ST W EB PARKING LANE CLOSED AT AVE J S
(Water main work)
Start: June 15, 7:00 a.m. End: June 19, 5:00 p.m.
AVE H S CLOSED FROM 22ND ST W TO 20TH ST W
(Water main work)
Start: June 15, 7:00 a.m. End: June 29, 5:00 p.m.
3RD AVE S NB & SB MEDIAN LANES CLOSED FROM 19TH ST E TO 22ND ST E
(Median restoration)
Start: June 15, 7:00 a.m. End: June 29, 5:00 p.m.
4TH AVE S NB PARKING LANE CLOSED FROM 20TH ST E TO 21ST ST E
(Landscaping)
Start: June 15, 7:00 a.m. End: June 29, 5:00 p.m.
AVE W S NB & SB MEDIAN LANES CLOSED FROM 11TH ST W TO APPLEBY DR
(Inspection)
Start: June 15, 8:00 a.m. End: June 16, 5:00 p.m.
11TH ST W EB CURB LANE CLOSED AT AVE W S
(Inspection)
Start: June 15, 8:00 a.m. End: June 16, 5:00 p.m.
1ST AVE N NB PARKING LANE CLOSED FROM 24TH ST E TO 25TH ST E
(Building construction)
Start: June 15, 8:00 a.m. End: July 31, 5:00 p.m.
24TH ST E EB & SB CURB LANE CLOSED AT 2ND AVE N
(Sewer maintenance)
Start: June 15, 9:00 a.m. End: June 15, 12:00 p.m.
CIRCLE DR E EB & WB MEDIAN LANES CLOSED ON CIRCLE DR NORTH BRIDGE
(Streetlight maintenance)
Start: June 15, 9:00 a.m. End: June 15, 3:00 p.m.
115TH ST E WB LANE CLOSED, NB CURB LANE CLOSED FROM KEEVIL WAY TO BERINI DR
(Construction)
Start: June 15, 9:00 a.m. End: June 16, 5:00 p.m.
25TH ST E WB LANES CLOSED FROM 2ND AVE N TO 1ST AVE N
(SL&P)
2-way traffic in EB lanes
Start: June 15, 9:00 a.m. End: July 10, 5:00 p.m.
ONGOING
71ST ST E CLOSED FROM IDYLWYLD SERVICE RD TO ARONEC AVE
(Roadway resurfacing)
Start: June 14, 7:00 a.m. End: June 15, 5:00 p.m.
COLLEGE DR EB CURB LANE CLOSED FROM MUNROE AVE N TO WIGGINS AVE N
(Construction)
Start: June 1, 7:00 a.m. End: June 15, 5:00 p.m.
TAYLOR ST E EB CLOSED FROM PARK AVE TO GROSVENOR AVE
(Sidewalk replacement)
Start: June 10, 7:00 a.m. End: June 15, 5:00 p.m.
20TH ST E EB CURB LANE CLOSED FROM IDYLWYLD DR S TO 1ST AVE S
(Streetscaping)
Start: June 10, 7:00 a.m. End: June 16, 5:00 p.m.
115TH ST E WB LANES CLOSED FROM KENDERDINE RD TO BERINI DR
(Concrete Preservation)
Two-way traffic in EB lanes
Start: June 4, 7:00 a.m. End: June 18, 5:00 p.m.
20TH ST W EB CURB LANE CLOSED FROM AVE L S TO AVE N S
(Construction)
Start: June 9, 7:00 a.m. End: June 19, 5:00 p.m.
20TH ST W EB CURB LANE CLOSED FROM AVE P S TO AVE O S
(Construction)
Start: June 10, 7:00 a.m. End: June 20, 5:00 p.m.
20TH ST W WB PARKING & CURB LANE CLOSURE. FROM AVE B S TO AVE B S
(Streetscaping)
Start: June 8, 7:00 a.m. End: June 21, 5:00 p.m.
20TH ST E WB CURB LANE CLOSED FROM 1ST AVE S TO IDYLWYLD DR S
(Streetscaping)
Start: June 10, 7:00 a.m. End: June 24, 5:00 p.m.
8TH ST E SB/WB/EB CUMBERLAND AVE INTERSECTION
(Link Station Construction)
Start: June 8, 7:00 a.m. End: June 30, 5:00 p.m.
PRESTON AVE S NB FROM LOUISE AVE TO ADELAIDE ST E
(Link Station Construction)
Two-way traffic to be maintained in the SB lanes
Start: June 8, 7:00 a.m. End: July 3, 5:00 p.m.
COLLEGE DR EB/WB UNIVERSITY BRIDGE
(College Dr Link Construction)
Closure of College Dr includes a full closure of the University Bridge at Spadina Cr E
Start: April 6, 7:00 a.m. End: July 13, 5:00 p.m.
SPADINA CRES E NB REDUCED LANE WIDTH AT 25TH ST E
(Construction)
Start: April 28, 7:00 a.m. End: August 8, 5:00 p.m.
WANUSKEWIN RD NB CLOSED FROM MARQUIS DR W TO 72ND ST E
(Construction)
Two-way traffic in NB lanes
Start: May 11, 9:00 a.m. End: October 9, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.