Daily Road Report - March 4, 2026
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
RUSSELL RD NB LANES CLOSED FROM LENORE DR TO NORDSTRUM RD
(Pole replacement)
Two-way traffic will be maintained in the SB lanes.
Start: March 4, 9:00 a.m. End: March 4, 3:00 p.m.
8TH ST E WB CURB LANE CLOSED FROM LORNE AVE TO MCPHERSON AVE
(Tree maintenance)
Start: March 4, 9:00 a.m. End: March 4, 3:00 p.m.
ONGOING
33RD ST W ROAD CLOSED FROM AVE F N TO AVE G N
(Connection replacement)
Start: March 3, 7:00 a.m. End: March 4, 5:00 p.m.
2ND AVE N SB LANES CLOSED & NB MEDIAN LANE CLOSED FROM 24TH ST E TO 25TH ST E
(Library construction)
Start: March 2, 8:00 a.m. End: March 5, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.