NEW

CLARENCE AVE S SB PARKING LANE CLOSED FROM 1ST ST E TO TAYLOR ST E
(Roadway patching)
Start: October 19, 7:00 a.m. End: October 19, 5:00 p.m.

AVE H N INTERSECTION CLOSED AT 32ND ST W
(Water main replacement)
Start: October 19, 7:00 a.m. End: October 20, 5:00 p.m.

BOYCHUK DR INTERSECTION CLOSED AT BRANDON PL
(Channelization)
Start: October 19, 7:00 a.m. End: October 27, 5:00 p.m.

CIRCLE DR E NB MEDIAN LANE & SB CURB LANE CLOSED AT WARMAN RD
(Cable pull)
Start: October 19, 9:00 a.m. End: October 19, 3:00 p.m.

IDYLWYLD DR N NB CURB LANE CLOSED FROM 28TH ST W TO 29TH ST E
(Sewer connection repair)
Start: October 19, 9:00 a.m. End: October 22, 3:00 p.m.

 

ONGOING

33RD ST E EB MEDIAN LANE CLOSED FROM QUEBEC AVE TO 1ST AVE N
(Construction)
Start: October 18, 8:00 a.m. End: October 19, 6:00 p.m.

NELSON RD ROAD CLOSED FROM HEAL AVE TO HEATH AVE
(Connections work)
Start: October 18, 8:00 a.m. End: October 21, 5:00 p.m.

COLLEGE DR EB CURB LANE & SHOULDER CLOSED FROM MCKERCHER DR TO PETERS COVE
(Roadwork)
Start: October 12, 7:00 a.m. End: October 25, 4:00 p.m.

NEAULT RD NB CLOSED FROM 22ND ST W TO 33RD ST W
(Water main construction)
Temporary traffic lights allowing alternating traffic flow
Start: September 20, 10:00 a.m. End: October 25, 5:00 p.m.

BRIGHTON BLVD ROAD CLOSED FROM 8TH ST TO BRIGHTON COMMON              
(Storm sewer work)          
Start: August 30, 9:00 a.m. End: October 31, 7:00 a.m. 

8TH ST E INTERSECTION CLOSED NEW MCORMOND DR
(Construction)
Start: April 26, 7:00 a.m. End: October 31, 7:00 a.m.
 