Major project starts on Circle Drive North Bridge February 28; two-way traffic in eastbound lanes
Construction is starting a little earlier than usual this year. On Tuesday, February 28, a nine-month-long rehabilitation will begin on the 40-year-old Circle Drive North Bridge. The project will start with a full closure of the westbound lanes with two-way traffic being accommodated in the eastbound lanes.
“When construction wraps up on the westbound side of the bridge in approximately four months from now, it will then reopen to accommodate two-way traffic while work happens on the eastbound side,” says Todd Grabowski, Engineering Manager, Asset Preservation. “It is unusual to start construction so early in the year, but because this is a major, months-long project on one of Saskatoon’s busiest roadways, we need to start early so we can finish during one construction season rather than extending the work over two.”
Grabowski says the City’s preservation plan, with the results of the Deck Testing Program, identified the need for the rehabilitation of the Circle Drive North Bridge to optimize the service life and diminish the overall capital lifecycle costs.
“Certain elements of the bridge are nearing the end of their typical lifecycle, so this is a proactive construction project to ensure it lasts for years to come. Work will include replacing asphalt and barriers, improvements to drainage and concrete, and repairs to the piers and abutments.”
The pedestrian bridge underneath the Circle Drive North Bridge will not be impacted during the rehabilitation project. A section of Spadina Crescent underneath the bridge will close at some points during construction to accommodate scaffolding.
“We know this construction project is going to be a pain in the asphalt because moving through this area of Circle Drive will be much slower than usual. We will continually monitor traffic and adjust signals throughout the city as necessary to minimize delays and disruptions as much as possible,” says Grabowski.
The 275-metre-long bridge opened in 1983 at a cost of $11.8 million. In 2005, additional lanes were added on each side of the bridge and in 2007, the pedestrian bridge opened.
For more information about the Circle Drive North Rehabilitation project, please visit saskatoon.ca/construction.