Multi-Purpose Remai Modern Gallery 90% Complete
Construction of Remai Modern is heading into the final stage – 90 per cent of the building contract is complete. While Remai Modern is first and foremost a world-class art museum, it is also a multi-purpose community facility.
“The beauty of Remai Modern is that it will be more than just an exceptional art gallery,” says Jeanna South, Special Projects Manager. “It will be a gathering place for both everyday events, and special occasions – a place to have dinner before an evening of live theatre, to shop, or to get married.”
The interior and gallery spaces are taking shape. Much has happened since the community last had a look in September. The construction is highlighted in a report to the Standing Policy Committee on Environment, Utilities & Corporate Services for Monday, May 9. Many items are nearing completion with significant progress on others:
- Bronze-coloured metal panel cladding on the East, North and West sides
- Interior atrium glass on levels three and four
- Walls and ceilings in the vault spaces
- Wall finishes in level two and three Gallery spaces
- Elevator installation is complete and final finishing is underway
- Preparation for the installation of the wood ceiling is underway. Final installation of the wood will occur late in the project, once environments are stable.
“We’re delighted that the construction of Remai Modern has reached more than 90 per cent completion,” says Gregory Burke, Remai Modern Executive Director and CEO.
“As construction proceeds, gallery staff members are going full-tilt on planning the exhibitions and programs that will animate the museum from top to bottom. It’s a spectacular building on a unique site, and we’re determined to offer visitor experiences that are equally amazing.”
The contractor is currently estimating completion of the contract in late 2016. The gallery is expected to open to the community in early 2017.