UNIVERSITY BRIDGE REHABILITATION: UPDATE
Rehabilitation of the iconic University Bridge is progressing well with crews nearing the completion of repairs to the bridge deck.
“We are very happy with the progress during this second phase of rehabilitation,” says Rob Frank, Manager of Asset Preservation. “As with the first phase, we have encountered no major issues. The dry weather also continued which has allowed the work to progress at a steady pace.”
While more work on the bridge will be undertaken this summer, it is expected that the bridge will reopen to vehicle traffic at least two to three weeks earlier than expected.
“Currently the concrete on the north side of the bridge is curing,” says Frank. “The contractor still needs to complete some grinding and smoothing work, approach paving, crack filling, expansion joint gland installation, pedestrian hand rail installations and site cleanup – as soon as this work is completed we can open the bridge.”
After the concrete has cured for 28 days, the deck will need to be sealed and permanent lane markings installed. This work will require some lane restrictions during off-peak hours. Rehabilitation work will also continue under the bridge. The City’s priority is to open the bridge to traffic as soon as possible.
The City thanks everyone for their patience during this project. This necessary work will ensure the 100 year old bridge will continue to serve commuters for many years to come. For more information visit saskatoon.ca/universitybridge.