University Bridge scheduled to reopen to traffic the week of June 29, Link work continues on College Drive
Work continues on College Drive as part of the Link project as well as the University Bridge arch rehabilitation project.
University Bridge and College Drive at Clarence Avenue are on track to re-open to two-way traffic, with one lane in each direction, during the week of June 29.
The College Drive work is proceeding on budget but has experienced early-stage delays due to weather, utility relocations and the unexpected discovery and removal of legacy underground infrastructure, including former building foundations, basements and historic trolley rails within the roadway.
Drivers are asked to follow posted detours and use caution when travelling near construction zones.
For more information about current road restrictions and construction, visit saskatoon.ca/construction. More information on Link is available at saskatoon.ca/Link.