25th Street closures scheduled for downtown watermain work
As crews continue watermain rehabilitation on 25th Street East, temporary closures and traffic restrictions will be required as work progresses along the corridor. The following impacts are scheduled:
Starting on July 27, 25th Street East eastbound lane will be fully closed between 2nd Avenue and 3rd Avenue for one day. Two-way traffic will be maintained.
Starting on July 28, work will take place between 3rd Avenue and 4th Avenue. Two-way traffic will be maintained, but motorists should expect delays.
Starting on July 29, work will take place between 4th Avenue and 5th Avenue. Two-way traffic will be maintained, but delays are expected.
Starting on July 30, work will take place between 5th Avenue and 6th Avenue. Two-way traffic will be maintained, but motorists should expect delays.
Work is weather dependent and subject to change due to unforeseen circumstances.
Drivers are encouraged to plan ahead, follow posted signage and use caution when travelling near construction zones.
For more information about current road restrictions and construction projects, visit saskatoon.ca/construction.