DAILY ROAD REPORT, AUGUST 31
NEW
CIRCLE DR WB CENTRE LANE CLOSED AT IDYLWYLD DR N
(Manhole flushing)
Start: August 31, 5:00 a.m. End: August 31, 7:00 a.m.
CENTRAL AVE SB/NB LANE RESTRICTIONS APPROACHING 104TH ST W
(Road paving)
Two-way traffic set up in NB lanes
Start: August 31, 9:00 a.m. End: August 31, 4:00 p.m.
NIGHT WORK: CIRCLE DR EB/WB CURB (OUTSIDE) LANES CLOSED AT CIRCLE DR NORTH BRIDGE
(Bridge deck sealing)
Start: August 31, 9:00 p.m. End: September 1, 5:00 a.m.
ONGOING
IDYLWYLD DR N/HIGHWAY 16 NB & SB LANE RESTRICTIONS FROM 51ST ST E TO MARQUIS DR W
(Hwy 16 flyover repair)
Start: July 13, 9:00 a.m. End: September 11, 5:00 p.m.
HWY 11/16 WB OVERPASS CLOSED AT CLOVERLEAF INTERSECTION
(Overpass repair)
Two EB lanes and one WB lane will be maintained on the EB overpass
Start: July 24, 7:00 a.m. End: September 30, 5:00 p.m.
MELVILLE ST EB LANES CLOSED FROM LORNE AVE TO BRAND RD
(Force main installation)
Start: August 24, 7:00 a.m. End: October 30, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.
Know before you go! Plan your route around road work by checking our Road Restrictions and Construction Projects interactive map. Find traffic detour information and subscribe to Traffic Detour Service Alerts at saskatoon.ca/service-alerts. You can also follow us on Twitter @YXEServiceAlert and with #betterroadsYXE and like Saskatoon City News on Facebook.