NEW 
 
NELSON RD ROAD CLOSED FROM HEATH AVE TO HEAL AVE 
(Crane setup) 
Start: July 8, 6:00 a.m. End: July 8, 2:00 p.m. 
 
33RD ST E EB LEFT TURN LANE CLOSED AT WARMAN RD 
(Construction) 
Start: July 8, 9:00 a.m. End: July 9, 5:00 p.m. 
 
WARMAN RD NB MEDIAN LANE CLOSED FROM LAURISTON ST TO 34TH ST E 
(Intersection improvements) 
Start: July 8, 9:00 a.m. End: July 9, 5:00 p.m. 
 
ONGOING 
 
MCKERCHER DR NB LANES CLOSED FROM TAIT CRES TO PARKDALE RD 
(Hydrant replacement) 
Start: July 7, 8:00 a.m. End: July 8, 4:30 p.m. 
 
IDYLWYLD DR N NB CURB LANE CLOSED FROM 51ST ST E TO MARQUIS DR E 
(Roadway resurfacing) 
Closures will be set each night and removed the following morning. 
Start: July 6, 6:30 p.m. End: July 9, 7:00 a.m. 
 
2ND AVE ROAD CLOSED FROM 20TH ST E TO 23RD ST E  
(Downtown Sidewalk Sale)  
Intersection at 2nd Avenue and 22nd Street will remain open  
Start: July 7, 5:30 a.m. End: July 9, 7:00 p.m. 
 
21ST ST E FULL CLOSURE FROM 1ST AVE S TO 2ND AVE S 
(Downtown Sidewalk Sale) 
Start: July 7, 5:30 a.m. End: July 9, 7:00 p.m. 
 
CIRCLE DR E EB & WB MEDIAN LANES CLOSED FROM QUEBEC AVE TO VENTURE CRES 
(Concrete replacement) 
Start: July 5, 7:00 a.m. End: July 10, 5:00 p.m. 
 
CLARENCE AVE S INTERSECTION CLOSED AT BUTE ST 
(Construction) 
Start: June 23, 7:00 a.m. End: July 11, 5:00 p.m. 
 
1ST AVE N NB PARKING LANE & SIDEWALK CLOSED FROM 23RD ST E TO 24TH ST E 
(Cable work) 
Start: July 4, 8:00 a.m. End: July 13, 4:30 p.m. 
 
WARMAN RD SB CURB LANE CLOSED AT 33RD ST E 
(Intersection improvements) 
Start: June 23, 7:00 a.m. End: July 14, 5:00 p.m. 
 
33RD ST E WB CURB LANE CLOSED AT WARMAN RD 
(Intersection improvements) 
Start: June 23, 7:00 a.m. End: July 14, 5:00 p.m. 
 
ATTRIDGE DR EB & WB MEDAIN LANES CLOSED AT CIRCLE DR E  
(Overpass rehabilitation)  
Start: July 5, 8:00 p.m. End: July 16, 7:30 p.m. 
 
DUNDONALD AVE SB CURB LANE CLOSED FROM 11TH ST W TO CAEN ST 
(Drainage improvements) 
Start: June 28, 7:00 a.m. End: July 25, 4:30 p.m. 
 
3RD AVE N ROAD CLOSED FROM 25TH ST TO QUEEN ST    
(Water main repair)    
Start: June 14, 7:00 a.m. End: July 29, 5:00 p.m. 
 
MCORMOND DR ROAD CLOSED AT BRIGHTON BLVD    
(New road construction)    
Start: June 29, 7:00 a.m. End: August 8, 5:00 p.m. 
 
RUTH ST E INTERSECTION CLOSED AT CAIRNS AVE 
(Water main replacement) 
Start: June 29, 7:00 a.m. End: August 22, 5:00 p.m. 
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances. 