Daily Road Report – May 22
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
TAYLOR ST E EB MEDIAN LANE CLOSED FROM ACADIA DR TO KINGSMERE BLVD
(Construction)
Start: May 22, 7:00 a.m. End: May 26, 4:00 p.m.
AVE H N ROAD CLOSED FROM 29TH ST W TO 30TH ST W
(Service connection replacement)
Start: May 22, 8:00 a.m. End: May 23, 12:00 p.m.
71ST ST E ROAD CLOSED FROM BURRON AVE TO ARONEC AVE
(Construction)
Start: May 22, 9:00 a.m. End: May 29, 5:00 p.m.
CIRCLE DR S WB CURB LANE AND RAMP CLOSED FROM CIRCLE DR E TO CIRCLE DR S
(Road resurfacing)
Start: May 22, 7:00 p.m. End: May 23, 6:00 a.m.
ONGOING
CIRCLE DR S WB CURB LANE & RAMPS CLOSED FROM MACLEAN CRES TO MENDEL COVE
(Road resurfacing)
Start: May 21, 7:00 p.m. End: May 22, 6:00 a.m.
1ST AVE N NB PARKING LANE CLOSED, WB PARKING LANE CLOSED AT 23RD ST E
(Construction)
Start: May 21, 8:00 a.m. End: May 22, 5:00 p.m.
DIEFENBAKER DR EB CLOSED FROM MOWAT CRES TO SMALLWOOD CRES
(Service connection replacement)
Start: May 21, 8:00 a.m. End: May 22, 5:00 p.m.
DIEFENBAKER DR EB CLOSED AT MOWAT CRES
(Water main work)
Start: May 21, 9:00 a.m. End: May 22, 5:00 p.m.
JUNOR AVE VARIOUS LANE CLOSURES AT MCCLOCKLIN RD
(Underground maintenance)
Start: May 20, 9:00 a.m. End: May 22, 5:00 p.m.
WANUSKEWIN RD SB LANES CLOSED FROM MARQUIS DR E TO 72ND ST E
(Construction)
Start: April 27, 7:00 a.m. End: May 22, 6:00 p.m.
TAYLOR ST E EB MEDIAN LANE CLOSED FROM ACADIA DR TO KINGSMERE BLVD
(Construction)
Start: May 20, 7:00 a.m. End: May 23, 4:00 p.m.
8TH ST E WB CURB LANE CLOSED FROM BOYCHUK DR TO CHABEN PL
(Construction)
All intersections will remain open
Start: May 11, 7:00 a.m. End: May 24, 5:00 p.m.
25TH ST E EB, SB & WB CURB LANE CLOSED FROM 2ND AVE N TO 1ST AVE N
(SL&P work)
Start: May 11, 9:00 a.m. End: May 25, 5:00 p.m.
TAYLOR ST E EB MEDIAN LANE CLOSED FROM ACADIA DR TO KINGSMERE BLVD
(Construction)
Start: May 21, 7:00 a.m. End: May 25, 4:00 p.m.
11TH ST W EB & WB CLOSED FROM AVE J S TO AVE I S
(Construction)
Start: April 20, 7:00 a.m. End: May 27, 5:00 p.m.
MCORMOND DR REDUCED LANES FROM KERR RD TO ADDISON RD
(road rehabilitation)
Start: May 19, 8:00 a.m. End: May 27, 5:00 p.m.
ACADIA DR ROAD CLOSED FROM TAYLOR ST E TO AVONDALE RD
(Water main maintenance)
Start: March 23, 7:00 a.m. End: June 1, 5:00 p.m
COLLEGE DRIVE ROAD CLOSED FROM CLARENCE AVE N TO UNIVERSITY DR
(Link construction)
Start: April 6, 7:00 a.m. End: June 1, 2026
20TH ST W WB CURB LANE CLOSED FROM 1ST AVE S TO IDYLWYLD DR S
(SL&P work)
Start: March 9, 9:00 a.m. End: June 5, 5:30 p.m.
COLLEGE DR EB/WB AND UNIVERSITY BRIDGE
(College Dr Link Construction)
Closure of College Dr includes a full closure of the University Bridge at Spadina Cr E
Start: April 6, 7:00 a.m. End: July 13, 5:00 p.m.
WANUSKEWIN RD NB & SB CLOSED FROM ARTHUR ROSE AVE TO MARQUIS DR E
(Construction)
Start: April 27, 7:00 a.m. End: June 14, 5:00 p.m.
SPADINA CRES E NB REDUCED LANE WIDTH AT 25TH ST E
(Construction)
Start: April 28, 7:00 a.m. End: August 8, 5:00 p.m.
21ST ST W ROAD CLOSED FROM AVE Y S TO AVE V S
(Cahill Park storm pond)
Start: May 11, 9:00 a.m. End: August 11, 5:00 p.m.
3RD AVE N NB PARKING LANE CLOSED FROM 22ND ST E TO 23RD ST E
(Building construction)
Start: May 18, 7:00 a.m. End: August 18, 5:00 p.m.
5TH AVE N CURB AND PARKING LANE CLOSURE FROM 25TH ST E TO 26TH ST E
(Building Construction)
Parking Lane on east-side of 5th Ave N is closed while construction takes place
Start: April 6, 7:00 a.m. End: August 28, 5:00 p.m.
1ST AVE N SB PARKING LANE CLOSED FROM 42ND A ST E TO CIRCLE DR E
(Building construction)
Start: May 1, 8:00 a.m. End: October 1, 5:00 p.m.
WANUSKEWIN RD NB CLOSED FROM MARQUIS DR W TO 72ND ST E
(Construction)
2-way traffic in NB lanes
Start: May 11, 9:00 a.m. End: October 9, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.