Daily Road Report - May 27
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
24TH ST W ROAD CLOSED FROM AVE C N TO AVE D N
(SaskEnergy)
Start: May 27, 7:00 a.m. End: May 27, 7:00 p.m.
20TH ST W WB CURB LANE CLOSED AT AVE O S
(Traffic calming)
Start: May 27, 7:00 a.m. End: June 5, 5:00 p.m.
20TH ST W WB CURB LANE CLOSED AT AVE M S
(Traffic calming)
Start: May 27, 7:00 a.m. End: June 5, 5:00 p.m.
KENSINGTON BLVD ROAD CLOSED FROM ELLS CRES TO ELLS CRES
(Homeland Trenching)
Start: May 27, 8:00 a.m. End: June 10, 5:00 p.m.
33RD ST E WB CLOSED FROM SPADINA CRES E TO EDWARD AVE
(Repair Catch Basin )
Start: May 27, 9:00 a.m. End: May 27, 12:00 p.m.
CIRCLE DR E WB MEDIAN LANE CLOSED FROM WARMAN RD SB RAMP TO WARMAN RD
(Sewer inspections)
Start: May 27, 9:00 a.m. End: May 27, 3:00 p.m.
CIRCLE DR E SB CURB LANE CLOSED FROM 8TH ST E TO TAYLOR ST E
(Streetlight Cable Fault)
Start: May 27, 9:00 a.m. End: May 27, 3:00 p.m.
14TH ST E ROAD CLOSED AT PRESTON AVE N
(BRT traffic signals)
14th St EB & WB closed at Preston Ave
Start: May 27, 9:00 a.m. End: May 27, 3:00 p.m.
CIRCLE DR S WB MEDIAN LANE CLOSED FROM HIGHWAY 11 TO MIDDLETON CRES
(Overnight Road resurfacing)
Start: May 27, 7:00 p.m. End: May 28, 6:00 a.m.
ONGOING
HIGHWAY 16 EB & WB MEDIAN LANES CLOSED AT HIGHWAY 11
(Overnight paving)
Start: May 26, 7:00 p.m. End: May 27, 6:00 a.m.
21ST ST W EB FROM AVE R S TO AVE P S
(St Paul's Hospital Community Day (Special Event))
Start: May 26, 4:00 p.m. End: May 27, 4:00 p.m.
11TH ST W EB & WB CLOSED FROM AVE J S TO AVE I S
(Water main work)
Start: April 20, 7:00 a.m. End: May 27, 5:00 p.m.
MCCLOCKLIN RD ROAD CLOSED FROM RICHARDSON RD TO DENHAM WAY
(Channelization)
Start: May 25, 7:00 a.m. End: May 27, 5:00 p.m.
IDYLWYLD DR N SB ROAD CLOSED FROM 27TH ST W TO 31ST ST W
(Construction)
Two-way will be maintained in the NB lanes. Intersection at 29th St will remain open.
Start: May 26, 9:00 a.m. End: May 28, 5:00 p.m.
71ST ST E ROAD CLOSED FROM BURRON AVE TO ARONEC AVE
(Marquis Phase 11A3 - W&S/AG/Roadways)
Start: May 22, 9:00 a.m. End: May 29, 5:00 p.m.
ACADIA DR NB & SB CLOSED, WB CURB LANE CLOSED. FROM TAYLOR ST E TO AVONDALE RD
(Water main work)
Start: March 23, 7:00 a.m. End: June 1, 5:00 p.m.
20TH ST W WB CURB LANE CLOSED FROM 1ST AVE S TO IDYLWYLD DR S
(Vault 1-2 Roof Replacement)
Start: March 9, 9:00 a.m. End: June 5, 5:30 p.m.
WANUSKEWIN RD NB & SB CLOSED FROM ARTHUR ROSE AVE TO MARQUIS DR E
(BPC Project)
Start: April 27, 7:00 a.m. End: June 14, 5:00 p.m.
MUNROE AVE N FULL CLOSURE FROM COLLEGE DR TO ELLIOTT ST
(Building Construction)
Start: June 24, 7:00 a.m. End: June 26, 5:00 p.m.
COLLEGE DR EB/WB UNIVERSITY BRIDGE
(College Dr Link Construction)
Closure of College Dr includes a full closure of the University Bridge at Spadina Cr E
Start: April 6, 7:00 a.m. End: July 13, 5:00 p.m.
SPADINA CRES E NB REDUCED LANE WIDTH AT 25TH ST E
(Construction)
Start: April 28, 7:00 a.m. End: August 8, 5:00 p.m.
21ST ST W ROAD CLOSED FROM AVE Y S TO AVE V S
(Cahill Park Storm Pond)
Start: May 11, 9:00 a.m. End: August 11, 5:00 p.m.
WANUSKEWIN RD NB CLOSED FROM MARQUIS DR W TO 72ND ST E
(Construction)
Two-way traffic in NB lanes
Start: May 11, 9:00 a.m. End: October 9, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.