Daily Road Report - October 9, 2025
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
8TH ST E EB LANES CLOSED FROM MCKERCHER DR TO BOYCHUK DR
(Traffic pole installations)
Two-way traffic will be maintained in WB lanes
Start: October 9, 6:00 a.m. End: October 9, 11:00 a.m.
PRESTON AVE S SB LEFT TURN LANE CLOSED AT ARMISTICE WAY
(Sanitary sewer lining)
Start: October 9, 7:00 a.m. End: October 30, 5:00 p.m.
PRESTON AVE S SB MEDIAN LANE CLOSED FROM LOUISE AVE TO EAST DRIVE
(Laydown area)
Start: October 9, 7:00 a.m. End: November 5, 5:00 p.m.
CLARENCE AVE S ROAD CLOSED FROM RUTH ST E TO ADELAIDE ST E
(Service connection replacement)
Start: October 9, 8:00 a.m. End: October 10, 12:00 p.m.
FAITHFULL AVE SB LANES CLOSED AT 56TH ST E
(Construction)
Start: October 9, 9:00 a.m. End: October 9, 12:00 p.m.
IDYLWYLD DR N NB MEDIAN LANE CLOSED FROM 24TH ST E TO 25TH ST E
(Water main maintenance)
Start: October 9, 9:00 a.m. End: October 9, 1:00 p.m.
IDYLWYLD DR N SB MEDIAN LANE CLOSED FROM 24TH ST E TO JAMIESON ST
(Water main maintenance)
Start: October 9, 9:00 a.m. End: October 9, 1:00 p.m.
24TH ST E EB CURB LANE CLOSED FROM 5TH AVE N TO 6TH AVE N
(Underground maintenance)
Start: October 9, 9:00 a.m. End: October 9, 3:00 p.m.
COLLEGE DR WB CURB LANE CLOSED FROM MCKERCHER DR TO CENTRAL AVE
(Sign repair)
Start: October 9, 9:00 a.m. End: October 9, 3:00 p.m.
MARQUIS DR E EB CURB LANE CLOSED AT MILLAR AVE
(Pole repairs)
Start: October 9, 9:00 a.m. End: October 9, 3:00 p.m.
MILLAR AVE NB & SB CURB LANES CLOSED AT MARQUIS DR E
(Pole repairs)
Start: October 9, 9:00 a.m. End: October 9, 3:00 p.m.
22ND ST W EB CURB & CENTER LANES CLOSED FROM AVE C S TO AVE B S
(Catch basin repair)
Start: October 9, 10:00 a.m. End: October 9, 1:00 p.m.
22ND ST W EB CURB LANE CLOSED FROM AVE F S TO AVE E S
(Lane reconstruction)
Start: October 9, 10:00 a.m. End: October 9, 2:00 p.m.
RUTH ST W ROAD CLOSED FROM ST HENRY AVE TO ST HENRY AVE
(Road work)
Start: October 9, 10:00 a.m. End: October 13, 5:00 p.m.
8TH ST E WB LANES CLOSED FROM MCKERCHER DR TO LUTHER PL
(Traffic pole installations)
Start: October 9, 11:00 a.m. End: October 9, 4:00 p.m.
ONGOING
PRESTON AVE S NB MEDIAN LANE CLOSED FROM EAST DRIVE TO LOUISE ST
(Sewer lining)
Start: October 6, 7:00 a.m. End: October 9, 11:00 a.m.
IDYLWYLD DR S NB & SB VARIOUS CLOSURES FROM CIRCLE DR S TO SASKATCHEWAN CRES E
(Mowing & Trimming)
Closures will be set daily from 9am to 3pm
Start: October 8, 9:00 a.m. End: October 9, 3:00 p.m.
8TH ST E WB CURB & CENTER LANES CLOSED FROM PRESTON AVE TO MCCOOL AVE
(Link station construction)
Start: October 8, 7:00 a.m. End: October 10, 7:00 a.m.
PRESTON AVE SB LANES CLOSED FROM 8TH ST E TO 7TH ST E
(Link station construction)
Start: October 8, 7:00 a.m. End: October 10, 7:00 a.m.
RUTH ST E INTERSECTION CLOSED FROM WIGGINS AVE S TO CUMBERLAND AVE S
(Construction)
Start: July 29, 7:00 a.m. End: October 10, 5:00 p.m.
4TH AVE N NB & SB MEDIAN LANES CLOSED AT 22ND ST E
(Water main maintenance)
Start: August 13, 7:00 a.m. End: October 10, 5:00 p.m.
WARMAN RD SB CURB LANE CLOSED AT 5TH AVE N
(Link station construction)
Start: September 19, 7:00 a.m. End: October 10, 5:00 p.m.
23RD ST E ROAD CLOSED FROM 3RD AVE N TO 4TH AVE N
(Water main maintenance)
Start: August 1, 7:00 a.m. End: October 10, 5:00 p.m.
24TH ST E WB LANES CLOSED FROM 1ST AVE N TO ONTARIO AVE
(SL&P work)
Start: October 7, 10:00 a.m. End: October 10, 5:00 p.m.
RUTH ST E ROAD CLOSED FROM LOUISE AVE TO JARVIS DR
(Water main construction)
Start: August 18, 7:00 a.m. End: October 10, 5:00 p.m.
ACADIA DR NB & SB CURB LANES CLOSED FROM 8TH ST E TO HIGHLANDS CRES
(Construction)
Start: October 8, 8:00 a.m. End: October 10, 5:00 p.m.
AVE H S ROAD CLOSED FROM 20TH ST W TO 22ND ST W
(Water & sewer connections)
Start: September 22, 7:00 a.m. End: October 11, 5:00 p.m.
4TH AVE N NB & SB MEDIAN LANES CLOSED AT 23RD ST E
(Water main maintenance)
Start: October 6, 7:00 a.m. End: October 12, 5:00 p.m.
MEADOWS PKY ROAD CLOSED FROM MEADOWS BLVD TO ZIMMERMAN RD
(Construction)
Start: October 6, 7:00 a.m. End: October 13, 5:00 p.m.
ASSINIBOINE DR WB LANES CLOSED FROM CHURCHILL DR TO RAVINE DR
(Concrete replacement)
Start: October 7, 7:00 a.m. End: October 17, 5:00 p.m.
CIRCLE DR W SB SPEED REDUCTION FROM AIRPORT DR TO 33RD ST W
(Construction)
Start: October 6, 9:00 a.m. End: October 17, 5:00 p.m.
8TH ST E EB & WB CURB LANES CLOSED AT MCKERCHER DR
(Link station construction)
Start: September 3, 7:00 a.m. End: October 17, 5:00 p.m.
8TH ST E WB & EB RIGHT TURN BAYS CLOSED AT MCKERCHER DR
(Link station construction)
Start: September 12, 7:00 a.m. End: October 17, 5:00 p.m.
MELVILLE ST INTERSECTION CLOSED AT JASPER AVE S
(Willows development)
Start: August 12, 7:00 a.m. End: October 17, 5:00 p.m.
MELVILLE ST ROAD CLOSED FROM JASPER AVE S TO PORTAGE AVE
(Sewer main installation)
Start: July 30, 7:00 a.m. End: October 17, 5:00 p.m.
LORNE AVE ROAD CLOSED FROM 3RD ST E TO 5TH ST E
(Water main preservation)
Start: September 26, 12:30 p.m. End: October 24, 5:00 p.m.
BERINI DR SB CURB LANE CLOSED FROM ATTRIDGE DR TO WEBSTER ST
(Construction)
Start: September 18, 8:00 a.m. End: October 28, 5:00 p.m.
ACADIA DR SB LANES & NB MEDIAN LANE CLOSED FROM AVONDALE RD TO TAYLOR ST E
(Water main maintenance)
Start: September 29, 7:00 a.m. End: October 31, 5:00 p.m.
22ND ST W EB CURB LANE CLOSED AT HART RD
(Link station construction)
Start: September 15, 8:00 a.m. End: October 31, 5:00 p.m.
BROADWAY AVE/BROADWAY BRIDGE CLOSED FROM 12TH ST E TO 20TH ST E
(Bridge rehabilitation)
Start: May 11, 7:00 p.m. End: October (Date TBA)
BRIGHTON BLVD ROAD CLOSED FROM TASKAMANWA ST TO 8TH ST E
(New road construction)
Use McOrmond Dr
Start: November 20, 7:00 a.m. End: November 28, 2025, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.