Beginning at 9:00 a.m. on Thursday, June 5, crews will begin paving sections of College Drive westbound. The work will be done in phases and the crews will move along the roadway section by section with the project expected to last 6 days.
The work is scheduled to progress in the following sequence:
- College Drive westbound curb (outside) lane
from the railroad track to McKercher Drive on ramp
- College Drive westbound curb (outside) lane
from McKercher Drive on ramp to Central Avenue
- College Drive westbound median (inside) lane
from the railroad track to Circle Drive overpass
- College Drive westbound curb (outside) lane
from Central Avenue to Circle Drive underpass and College Drive westbound on
ramp onto Circle Drive.
One lane on College Drive westbound will remain open at all times. Crews will be working around the clock to accelerate the length of construction and minimize impact to traffic.
Please watch for Traffic Detour alerts at Saskatoon.ca for up-to-date information on specific road restrictions in this area.
MILLAR AVENUE BETWEEN 46TH & 47TH STREETS, JUNE 5
Beginning at 7:00 a.m. on Thursday, June 5, Millar Avenue northbound lanes and the southbound median lane will be closed between 46th Street East and 47th Street East while crews repair a sanitary sewer connection.
The road is expected to reopen by 5:00 p.m. the same day.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.
Know before you go! Find traffic detour information on our website at www.saskatoon.ca/go/traffic. You can also follow us on Twitter @cityofsaskatoon and with #betterroadsYXE and like Saskatoon City News on Facebook.