SPC Committee on Transportation Decisions in Brief
From the November 14, 2016 Meeting
8.1.8 North Commuter Parkway and Traffic Bridge Construction Update
Decision
*The Committee received the report as information.
Background
*The project continues to be on time and on budget.
*At the Traffic Bridge, Graham Commuter Partners (GCP) has completed Pier 3 as well as the north and south bridge abutments. Span 4, the southernmost span of the bridge, has also been completed.
*Demolition of the last original Traffic Bridge span took place November 17, 2016.
*At the North Commuter Parkway bridge, construction of Pier 1, the west in-river pier, has been completed. Construction of Pier 2, the centre in-river pier, is underway with the pier foundation, diaphragm, and columns already complete, and construction of the pier cap currently underway.
*Earthworks for the new roadways subgrades is underway. Storm sewer installation for the new roadways is ongoing until the end of November.
8.1.10 Building Better Bridges: An Asset Management Plan for Bridges and Structures
Decision
*The Committee received the plan as information.
*Administration will provide a report for the 2017 Business Plan and Budget deliberations as part of the Corporate Management Plan.
Background
*The report shows the physical condition of bridges and structures. Currently, 29% of bridges, 58% of overpasses and 76% of pedestrian crossings are in good to very good condition.
*A potential funding plan is illustrated with the goal of bridging the funding gap to enable the assets to reach the desired condition over time.
8.1.11 Building Better Roadways: An Asset Management Plan for Roadways
Decision
*The Committee received the plan as information.
*Administration will provide a report for the 2017 Business Plan and Budget deliberations as part of the Corporate Management Plan.
Background
*The City’s roadway replacement value is estimated at $2.82 billion. In order to maintain the roadways in satisfactory to good condition, an annual investment of $26.2 million is required. This funding level will be reached in 2017 as the final year of a four year dedicated levy is completed.
8.1.12 Building Better Sidewalks: An Asset Management Plan for Sidewalks
Decision
*The Committee received the plan as information.
*Administration will provide a report for the 2017 Business Plan and Budget deliberations as part of the Corporate Management Plan.
Background
*The condition of sidewalks in Saskatoon range from ‘failed’ to ‘good’ condition depending on location. At a network level, the current overall, or system average, physical condition of sidewalks is considered to be satisfactory.
*Two potential funding plans are illustrated with the goals of bridging the funding gap to enable the assets to reach the desired condition of good over time and to show the cost of using asphalt overlays in comparison to not using asphalt overlays as a preservation strategy.
8.2.1 Building Better Sidewalks: Sidewalk Programs Overview
Decision
*The Committee recommended to City Council that Administration be directed to eliminate the practice of using asphalt overlays on concrete sidewalks and that funding for this service level be reallocated.
Background
*Capital Project #0948 – New Sidewalks and Pathways is a retrofit program to construct sidewalks and pathways at locations where they do not currently exist.
*Capital Project #1963 – Corporate Accessibility Implementation addresses the identified priorities of the Accessibility Service Level Guidelines, and a portion of this capital project includes accessibility ramp installations to address accessibility issues throughout Saskatoon.
*Capital Project #2270 – Neighbourhood Network and Primary Network Preservation Programs is administered by Major Projects and is a program to restore and maintain sidewalks in a safe condition for users, which involves repairing or replacing panels of sidewalks having trip hazards or missing sections.
*The Sidewalk Maintenance and Safety program is administered by Public Works and is a program to address spot repairs of sidewalk panels to address immediate safety concerns.
*Eliminating asphalt overlays from the treatments available for use, yet maintaining the same treatment coverage, would require an increase in funding of $2.2 million annually. This can be achieved with either a funding increase to the program or a re-distribution of funding allocations within the existing program
8.2.5 Update on Railway Working Group
Decision
*The report has been forwarded to City Council for consideration.
Background
*Modifications were made to Canadian National Railway’s (CN) operations in the south west portion of the city to reduce traffic delays in the area.
*Saskatoon Regional Economic Development Authority (SREDA) has completed a preliminary analysis of the economic impact of rail delays at key rail crossings throughout the city.
*The scope of the first phase of the grade separation and rail relocation feasibility study has been developed to compare both options.
*The second phase involves more detailed analysis on the chosen option.
8.2.6 Traffic Noise Sound Attenuation Policy Framework
Decision
*The Committee recommended to City Council:
1. That the Administration proceed with preparing a Council Policy based on the Traffic Noise Sound Attenuation policy framework provided in this report;
2. That the recommended Traffic Noise Sound Attenuation monitoring program be included in the Council Policy; and
3. That the report be considered during the 2017 Business Plan and Budget deliberations.
Background
*In 2013, a report was submitted to City Council during the 2014 Budget Deliberations and approved the construction of nine sound attenuation projects in Capital Project #1522 – Traffic Noise Sound Attenuation. The funds were to be borrowed and repaid over a 10-year period to complete these projects. City Council also requested a revised policy before additional locations on the priority list are funded and that the priority list be updated based on this policy. During consideration of the Capital Project #1522 – Traffic Noise Sound Attenuation report, the Standing Policy Committee on Transportation, at its meeting held on July 19, 2016, resolved: “That the matter be referred to the Administration to provide an update report regarding policy and standards prior to a report being submitted to the 2017 Business Plan and Budget deliberations.”