Weekend Road Report – May 30 & 31
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
CIRCLE DR E NB RAMP CLOSED AT IDYLWYLD DR N
(Roadway patching)
Use Faithful to 51st St for Circle Dr NB access
Start: May 30, 6:30 a.m. End: May 30, 8:30 a.m.
HEROLD RD NB & SB CLOSED, WB PARKING LANE CLOSED FROM PAWLYCHENKO LANE TO SLIMMON RD
(Road resurfacing)
Start: May 30, 7:00 a.m. End: May 31, 5:00 p.m.
ATTRIDGE DR NB MEDIAN LANE CLOSED FROM NELSON RD TO FORESTRY FARM PARK DR
(Overnight sewer inspections)
Start: May 30, 10:00 p.m. End: May 31, 6:00 a.m.
DIEFENBAKER PARK RD VARIOUS FROM ST HENRY AVE TO ST HENRY AVE
(Sask Marathon (Special Event))
Various road closures throughout the city
Start: May 31, 5:00 a.m. End: May 31, 2:00 p.m.
VICTORIA AVE VARIOUS FROM TAYLOR ST E TO 11TH ST E
(Sask Marathon (Special Event))
Police assisted at Taylor St/8th St/11th St intersections
Start: May 31, 5:00 a.m. End: May 31, 2:00 p.m.
TRAFFIC BRIDGE VARIOUS FROM 11TH ST E TO 19TH ST E
(Sask Marathon (Special Event))
Various closures along marathon route
Start: May 31, 5:00 a.m. End: May 31, 2:00 p.m.
SPADINA CRES E VARIOUS FROM BROADWAY AVE TO PINEHOUSE DR
(Sask Marathon (Special Event))
Various closures along the marathon route
Start: May 31, 5:00 a.m. End: May 31, 2:00 p.m.
CIRCLE DR E NB & SB MEDIAN LANES CLOSED FROM 8TH ST E TO 7TH ST E
(Streetlight pole replacement)
Start: May 31, 6:30 a.m. End: May 31, 8:00 a.m.
TAYLOR ST E ROAD CLOSED FROM JACKSON AVE TO MORGAN AVE
(Roadways)
Start: May 31, 7:00 a.m. End: May 31, 3:00 p.m.
TAYLOR ST E WB ROAD CLOSED AT WIGGINS AVE S
(Roadways)
Start: May 31, 7:00 a.m. End: May 31, 3:00 p.m.
SPADINA CRES W VARIOUS FROM SCHUYLER ST TO POWER RD
(Sask Marathon)
Various detours throughout the city
Start: May 31, 7:30 a.m. End: May 31, 1:00 p.m.
CIRCLE DR E NB & SB MEDIAN LANES CLOSED FROM 8TH ST E TO 14TH ST E
(Streetlight Hit by Car)
Start: May 31, 8:00 a.m. End: May 31, 10:00 a.m.
MCORMOND DR SB CLOSED AT BRIGHTON COMMON
(Streetlight replacement)
Start: May 31, 9:30 a.m. End: May 31, 11:00 a.m.
CIRCLE DR E EB & SB CURB LANES CLOSED AT CLARENCE AVE S
(SL&P work)
Start: May 31, 11:00 a.m. End: May 31, 12:30 p.m.
ONGOING
BROADWAY AVE SB CLOSED, NB LEFT TURN LANE CLOSED FROM MAIN ST TO 9TH ST E
(Construction)
Two-way traffic set in NB lanes.
Start: May 28, 7:00 a.m. End: May 31, 5:00 p.m.
ACADIA DR NB & SB CLOSED, WB CURB LANE CLOSED. FROM TAYLOR ST E TO AVONDALE RD
(Water main work)
Start: March 23, 7:00 a.m. End: June 1, 5:00 p.m.
20TH ST W WB CURB LANE CLOSED AT AVE O S
(Traffic calming)
Start: May 27, 7:00 a.m. End: June 5, 5:00 p.m.
20TH ST W WB CURB LANE CLOSED AT AVE M S
(Traffic calming)
Start: May 27, 7:00 a.m. End: June 5, 5:00 p.m.
20TH ST W WB CURB LANE CLOSED FROM 1ST AVE S TO IDYLWYLD DR S
(Vault 1-2 Roof Replacement)
Start: March 9, 9:00 a.m. End: June 5, 5:30 p.m.
KENSINGTON BLVD ROAD CLOSED FROM ELLS CRES TO ELLS CRES
(Homeland Trenching)
Start: May 27, 8:00 a.m. End: June 10, 5:00 p.m.
WANUSKEWIN RD NB & SB CLOSED FROM ARTHUR ROSE AVE TO MARQUIS DR E
(Construction)
Start: April 27, 7:00 a.m. End: June 14, 5:00 p.m.
COLLEGE DR EB/WB UNIVERSITY BRIDGE
(College Dr Link Construction)
Closure of College Dr includes a full closure of the University Bridge at Spadina Cr E
Start: April 6, 7:00 a.m. End: July 13, 5:00 p.m.
SPADINA CRES E NB REDUCED LANE WIDTH AT 25TH ST E
(Construction)
Start: April 28, 7:00 a.m. End: August 8, 5:00 p.m.
WANUSKEWIN RD NB CLOSED FROM MARQUIS DR W TO 72ND ST E
(Construction)
Two-way traffic in NB lanes
Start: May 11, 9:00 a.m. End: October 9, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.