Bridging to Tomorrow Project Update

For immediate release: April 21, 2016 - 9:38am
TU16-242

Since the February declaration of construction starting on the Bridging to Tomorrow project, the City and project partners, Graham Commuter Partners (GCP), have completed a substantial amount of work on both the North Commuter Parkway and the new Traffic Bridge.

Once complete in 2018, the North Commuter Parkway will support the transportation needs of citizens who live in Saskatoon’s northeast and work in the Marquis and North Industrial Areas, reducing traffic on the city’s existing bridges. The new Traffic Bridge, also slated for completion in 2018, will support the growing city centre by allowing motorists, pedestrians and cyclists to cross the river between the downtown and residential areas in the south sector of the city. The new bridge will look similar to the old bridge, but will be wider with the ability to accommodate emergency vehicles. 

Traffic Bridge Update – April 2016

Throughout the remainder of April, crews are continuing to work on refurbishing the south in-river pier (concrete column that supports the bridge deck), and are drilling piles to build the south abutment (supporting end of the bridge on the riverbank). The north berm that supported the bridge demolition has been removed, and crews have also finished removing part of the south berm to reduce impacts on river navigation. Later this spring and throughout summer, the southernmost pier will be reconstructed, the new north and south bridge abutments will be built, and the steel structure for the new southernmost span will be constructed.

North Commuter Parkway Update – April 2016

Parkway Bridge

A road has been constructed on the west side of the river to access the construction site. All regulatory permits to begin in-river construction have been received and work on an earthen berm to support construction of the first bridge pier has been built. By August, the first pier should be complete and work on the second pier will begin.

Parkway Roadways

Construction of the Parkway’s new roadways has begun. Clearing, topsoil stripping and ditch excavation are underway for the twinning and extension of Central Avenue to intersect with McOrmond Drive. This road will be extended to connect to the Parkway bridge. Earth has been moved to consolidate the ground under the future roadway in the Northeast Swale, and two clay berms (walls) have been installed through the Northeast Swale to prevent water from draining into the work zone. This work is being monitored by GCP’s environmental consultant and audited by the City’s technical advisor.

Improvements to the intersections of Central Avenue and Attridge Drive, and Marquis Drive and Wanuskewin Road, will begin in May.  

Traffic and Trails

Increased traffic will be evident at Marquis Drive and Wanuskewin Road with trucks hauling materials accessing the bridge construction site. Restrictions at Central Avenue and Attridge Drive, and at Marquis Drive and Wanuskewin Road, will begin in May and citizens will be notified of traffic detours through the City’s Daily Road Report, road signage, and social media.

Rotary Park and River Landing trail detours are in place and will continue through the construction period. Access to Crocus Prairie Trail from Central Avenue is closed until winter 2016. At times, the east sidewalk at Wanuskewin Road and Marquis Drive will be restricted for vehicle crossings.

Ways to Watch Construction Progress

Anyone interested can keep an eye on construction progress at saskatoon.ca/bridging. The webpage has a new quarterly video update, live project webcams, time lapse videos, and photographs. Construction viewing areas are also in place at River Landing and on the Meewasin Trail just north of the GCP construction trailer site at the intersection of Wanuskewin Road and Marquis Drive.

Stay Safe Near Construction Zones

Citizens are reminded to obey all traffic and Meewasin Trail detours in place, and to respect all safety measures in place including site fencing and site markings. The City is also reminding pedestrians to stay clear of work areas near the construction sites.

For more City of Saskatoon news, program information, Service Alerts, Traffic Detours, and links to our social media channels, please visit saskatoon.ca.