      Broadway Bridge to reopen Saturday evening
                          October 30, 2025 - 3:15pm
      
    
    Saskatoon’s Broadway Bridge is set to reopen on the evening of Saturday, November 1 following a nine-month long rehabilitation project. Barring any unforeseen circumstances, drivers, cyclists and pedestrians will once again have full access to the bridge.
“This was a major project that included deck repairs, improvements to the multi-use pathways, new asphalt, new waterproofing, new traffic barriers, arch and railing improvements and the removal of old and abandoned utilities underneath the bridge,” says Terry Schmidt, General Manager of Transportation and Construction.
One of the most significant changes has been the reconfiguration of the 4th Avenue and 19th Street intersection. To improve traffic safety and accommodate pedestrian movement, it is now a 'T' intersection.
“This intersection redesign supports future Saskatoon Transit Link plans and makes it easier for buses to navigate between Broadway Avenue and 19th Street,” Schmidt says. “The Broadway Bridge is a vital connection for our community, and these upgrades will serve all residents for decades to come.”
While the bridge and Spadina Crescent are reopening to vehicles and pedestrians, repairs will continue underneath the bridge. This work is not expected to impact traffic.
Saskatoon Transit will resume Route 8 service along Broadway Avenue once the bridge reopens. Service to temporary stops on Victoria Avenue and travel along the Traffic Bridge will end when regular service on Broadway resumes. Trip planning, service alerts and real-time bus information are available on third-party apps like Transit and Google Maps Transit on desktop.
      
      Daily Road Report - October 31, 2025
                          October 30, 2025 - 3:00pm
      
    
    *This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
IDYLWYLD DR N SB LANES CLOSED FROM 25TH ST E TO 23RD ST E 
(Water main break)
Two-way traffic will be maintained in the NB lanes 
Start: October 31, 7:00 a.m. Ends: October 31, 5:00 p.m.
3RD AVE N ROAD CLOSED FROM 22ND ST E TO 23RD ST E
(Water main work)
Start: October 31, 9:00 a.m. End: October 31, 11:00 a.m.
25TH ST E WB CURB LANE CLOSED FROM KINSMEN AVE TO 5TH AVE N
(Underground maintenance)
Start: October 31, 9:00 a.m. End: October 31, 12:00 p.m.
22ND ST W EB & WB LEFT TURN LANES CLOSED AT AVE C N
(Manhole repair)
Start: October 31, 9:00 a.m. End: October 31, 3:00 p.m.
23RD ST E ROAD CLOSED FROM 5TH AVE N TO 4TH AVE N
(Construction)
Start: October 31, 11:00 a.m. End: October 31, 1:00 p.m.
25TH ST E WB CURB LANE CLOSED FROM 5TH AVE N TO 4TH AVE N
(Underground maintenance)
Start: October 31, 12:00 p.m. End: October 31, 3:00 p.m.
4TH AVE N ROAD CLOSED FROM 22ND ST E TO 23RD ST E
(Construction)
Start: October 31, 1:00 p.m. End: October 31, 3:00 p.m.
5TH AVE N ROAD CLOSED FROM 22ND ST E TO 23RD ST E
(Water main work)
Start: October 31, 3:00 p.m. End: October 31, 4:00 p.m.
ONGOING
PRESTON AVE S SB MEDIAN LANE CLOSED FROM LOUISE AVE TO EAST DRIVE
(Construction)
Start: October 9, 7:00 a.m. End: November 5, 5:00 p.m.
BERINI DR SB CURB LANE CLOSED FROM ATTRIDGE DR TO WEBSTER ST
(Construction)
Start: September 18, 8:00 a.m. End: November 7, 5:00 p.m.
BROADWAY AVE/BROADWAY BRIDGE CLOSED FROM 12TH ST E TO 20TH ST E
(Bridge rehabilitation)
Start: May 11, 7:00 p.m. End: November (Date TBA)
CIRCLE DR W SB LANES SPEED REDUCTION FROM AIRPORT DR TO 33RD ST W
(Construction)
Start: October 6, 9:00 a.m. End: November 12, 5:00 p.m.
4TH AVE S ROAD CLOSED FROM 20TH ST E TO 19TH ST E
(Valve replacement)
Start: October 23, 7:00 a.m. End: November 12, 5:00 p.m.
MELVILLE ST ROAD CLOSED FROM JASPER AVE S TO PORTAGE AVE
(Sewer main installation)
Start: July 30, 7:00 a.m. End: November 21, 5:00 p.m.
BRIGHTON BLVD ROAD CLOSED FROM TASKAMANWA ST TO 8TH ST E
(New road construction)
Use McOrmond Dr
Start: November 20, 7:00 a.m. End: November 28, 2025, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.
      
      Idylwyld Drive southbound lanes closed between 25th and 23rd streets on Friday
                          October 30, 2025 - 1:30pm
      
    
    Southbound lanes of Idylwyld Drive will be closed between 25th and 23rd streets on Friday, October 31 starting at 7:00 a.m. for unplanned water main repairs. Two-way traffic will be maintained in the northbound lanes. This work is expected to take one day to complete, weather permitting and barring any unforeseen circumstances.
Saskatoon Transit may be affected by these detours. Transit service alerts and real-time bus information are available on third-party apps like Transit and Google Maps Transit on desktop.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.
      
      3rd Avenue closed between 22nd and 23rd streets on Friday
                          October 30, 2025 - 9:31am
      
    
    3rd Avenue will be closed between 22nd and 23rd streets on Friday, October 31, starting at 9:00 a.m. for water main work. Detours will be in place guiding motorists around the area. This project is expected to take two hours to complete, weather permitting and barring any unforeseen circumstances.
Saskatoon Transit may be affected by these detours. Transit service alerts and real-time bus information are available on third-party apps like Transit and Google Maps Transit on desktop.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.
      
      4th Avenue closed between 22nd and 23rd streets on Friday
                          October 30, 2025 - 8:49am
      
    
    4th Avenue will be closed between 22nd and 23rd streets on Friday, October 31, starting at 1:00 p.m. for construction work. Detours will be in place guiding motorists around the area. This project is expected to take two hours to complete, weather permitting and barring any unforeseen circumstances.
Saskatoon Transit may be affected by these detours. Transit service alerts and real-time bus information are available on third-party apps like Transit and Google Maps Transit on desktop.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.