News Releases
Saskatoon Fire - News Releases
Central Avenue closed between 109th and 110th streets on Wednesday
May 27, 2025 - 6:00am
Central Avenue will be closed between 109th and 110th streets on Wednesday, May 28, starting at 9:00 a.m. for roadway patching. Detours will be in place guiding motorists around the work zone. This project is expected to take one day to complete, weather permitting and barring any unforeseen circumstances.
Saskatoon Transit may be affected by these detours. Transit service alerts and real-time bus information are available on third-party apps like Transit and Google Maps Transit on desktop.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.
Daily Road Report - May 27, 2025
May 26, 2025 - 3:00pm
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
PRESTON AVE S SB MEDIAN LANE CLOSED FROM CORNISH RD TO STONEBRIDGE COMMON
(Underground maintenance)
Start: May 27, 7:00 a.m. End: May 27, 10:00 a.m.
22ND ST W EB CURB LANE CLOSED FROM CIRCLE DR W TO WITNEY AVE N
(Concrete repair)
Start: May 27, 7:00 a.m. End: May 27, 3:00 p.m.
11TH ST W EB LANES CLOSED FROM DAWES AVE TO AVE U S
(Environmental monitoring)
Start: May 27, 7:00 a.m. End: May 28, 5:00 p.m.
AVE P S ROAD CLOSED FROM 19TH ST W TO 20TH ST W
(Construction)
Start: May 27, 7:00 a.m. End: May 29, 5:00 p.m.
BROADWAY AVE ROAD CLOSED FROM 12TH ST E TO SASKATCHEWAN CRES E
(Link station construction)
Start: May 27, 7:00 a.m. End: June 2, 6:00 p.m.
MILLAR AVE SB LANES CLOSED FROM 58TH ST E TO 57TH ST E
(Roadway patching)
Two-way traffic will be maintained in NB lanes
Start: May 27, 9:00 a.m. End: May 27, 3:00 p.m.
CLARENCE AVE S SB MEDIAN LANE CLOSED FROM BRAND RD TO COPE CRES
(Junction box replacement)
Start: May 27, 10:00 a.m. End: May 27, 2:00 p.m.
KERR RD WB LANES CLOSED FROM KENDERDINE RD TO GILLAM CRES
(Water main maintenance)
Start: May 27, 11:00 a.m. End: May 27, 2:00 p.m.
8TH ST E EB CURB LANE CLOSED FROM ARLINGTON AVE TO CIRCLE DR E
(Underground maintenance)
Start: May 27, 12:00 p.m. End: May 27, 3:00 p.m.
TAYLOR ST E WB MEDIAN LANE CLOSED FROM BOYCHUK DR TO HERITAGE LANE
(Junction box replacement)
Start: May 27, 1:00 p.m. End: May 27, 4:00 p.m.
ONGOING
22ND ST W EB CURB & CENTRE LANES CLOSED FROM CIRCLE DR W TO WITNEY AVE N
(Concrete repair)
Start: May 26, 9:00 a.m. End: May 27, 7:00 a.m.
FAIRLIGHT DR WB LANES & EB MEDIAN LANE CLOSED AT FAIRMONT DR
(Paving)
Start: May 26, 8:00 a.m. End: May 27, 5:00 p.m.
3RD AVE S NB LANES CLOSED FROM TRAFFIC CIRCLE TO 19TH ST E
(Sewer main installation)
Start: May 20, 9:00 a.m. End: May 27, 5:00 p.m.
PRESTON AVE N NB LANES CLOSED FROM MAIN ST TO 14TH ST E
(Paving)
Start: May 26, 7:00 a.m. End: May 28, 5:00 p.m.
BALTZAN BLVD ROAD CLOSED FROM MARLATTE CRES TO ORBAN WAY
(Road repairs)
Start: May 26, 7:00 a.m. End: May 28, 7:00 p.m.
WARMAN RD SB RAMP CLOSED AT CIRCLE DR E
(Construction)
Start: May 12, 7:00 a.m. End: June 1, 5:00 p.m.
22ND ST W EB LANES & WB MEDIAN LANE CLOSED FROM AVE I N TO AVE K N
(Water main maintenance)
Two-way traffic will be maintained in WB lanes
Start: May 26, 7:00 a.m. End: June 1, 6:00 p.m.
CIRCLE DR W SB SPEED REDUCTION FROM GLENWOOD AVE TO 33RD ST W
(Jersey barrier placement)
Start: April 28, 7:00 a.m. End: June 2, 4:00 p.m.
BROADWAY AVE SB LANES CLOSED FROM SASKATCHEWAN CRES E TO 12TH ST E
(Link platform construction)
Start: May 20, 7:00 a.m. End: June 2, 4:30 p.m.
BOYCHUK DR SB CURB LANE CLOSED FROM 8TH ST E TO BRIARWOOD RD
(Sidewalk construction)
Start: May 16, 8:00 a.m. End: June 6, 5:00 p.m.
CUMBERLAND AVE S SB LANES CLOSED FROM 5TH ST E TO TAYLOR ST E
(Sidewalk replacements)
Two-way traffic will be maintained in NB lanes
Start: May 26, 7:00 a.m. End: June 7, 5:00 p.m.
BROADWAY AVE SB CURB & CENTER LANES CLOSED FROM 8TH ST E TO 9TH ST E
(Link station construction)
Start: May 26, 7:00 a.m. End: June 8, 4:30 p.m.
MCORMOND DR SB LANES CLOSED FROM NELSON RD TO ATTRIDGE DR
(Link station construction)
Start: May 26, 7:00 a.m. End: June 8, 5:00 p.m.
BRIGHTON BLVD ROAD CLOSED FROM TASKAMANWA ST TO 8TH ST E
(Construction)
Start: November 20, 7:00 a.m. End: September 26, 2025, 5:00 p.m.
BROADWAY BRIDGE CLOSED FROM 12TH ST E TO 20TH ST E
(Bridge rehabilitation)
Start: May 11, 7:00 p.m. End: October (Date TBA)
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.
Broadway Avenue closed between 12th Street and Saskatchewan Crescent starting Tuesday
May 26, 2025 - 6:00am
Broadway Avenue will be closed between 12th Street and Saskatchewan Crescent starting Tuesday, May 27, at 7:00 a.m. for Link station construction. Detours will be in place guiding motorists around the work zone. This project is expected to take six days to complete, weather permitting and barring any unforeseen circumstances.
Saskatoon Transit may be affected by these detours. Transit service alerts and real-time bus information are available on third-party apps like Transit and Google Maps Transit on desktop.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.
Daily Road Report - May 26, 2025
May 23, 2025 - 3:00pm
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
CUMBERLAND AVE S SB LANES CLOSED FROM MAIN ST TO 8TH ST E
(SL&P)
Start: May 26, 4:00 a.m. End: May 27, 5:00 p.m.
PRESTON AVE N NB LANES CLOSED FROM MAIN ST TO 14TH ST E
(Paving)
Start: May 26, 7:00 a.m. End: May 28, 5:00 p.m.
BALTZAN BLVD ROAD CLOSED FROM MARLATTE CRES TO ORBAN WAY
(Road repairs)
Start: May 26, 7:00 a.m. End: May 28, 7:00 p.m.
22ND ST W EB LANES & WB MEDIAN LANE CLOSED FROM AVE I N TO AVE K N
(Water main maintenance)
Two-way traffic will be maintained in WB lanes
Start: May 26, 7:00 a.m. End: June 1, 6:00 p.m.
CUMBERLAND AVE S SB LANES CLOSED FROM 5TH ST E TO TAYLOR ST E
(Sidewalk replacements)
Two-way traffic will be maintained in NB lanes
Start: May 26, 7:00 a.m. End: June 7, 5:00 p.m.
BROADWAY AVE SB CURB & CENTER LANES CLOSED FROM 8TH ST E TO 9TH ST E
(Link station construction)
Start: May 26, 7:00 a.m. End: June 8, 4:30 p.m.
MCORMOND DR SB LANES CLOSED FROM NELSON RD TO ATTRIDGE DR
(Link station construction)
Start: May 26, 7:00 a.m. End: June 8, 5:00 p.m.
FAIRLIGHT DR WB LANES & EB MEDIAN LANE CLOSED AT FAIRMONT DR
(Catch basin repairs)
Start: May 26, 8:00 a.m. End: May 26, 5:00 p.m.
2ND AVE N NB CURB LANE CLOSED FROM 24TH ST E TO 25TH ST E
(SL&P)
Start: May 26, 9:00 a.m. End: May 26, 1:00 p.m.
CIRCLE DR W MOBILE CLOSURE FROM 33RD ST W TO AIRPORT DR
(Median mowing)
Start: May 26, 9:00 a.m. End: May 26, 2:00 p.m.
IDYLWYLD DR S SB CURB LANE CLOSED FROM 11TH ST E TO IDYLWYLD PL
(Minor bridge repair)
Start: May 26, 9:00 a.m. End: May 26, 3:00 p.m.
22ND ST W EB CURB & CENTRE LANES CLOSED FROM CIRCLE DR W TO WITNEY AVE N
(Concrete repair)
Start: May 26, 9:00 a.m. End: May 27, 7:00 a.m.
ONGOING
IDYLWYLD DR S NB MEDIAN LANE CLOSED FROM 21ST ST E TO 22ND ST E
(Sewer main lining)
Start: May 25, 8:00 p.m. End: May 26, 2:00 a.m.
3RD AVE S NB LANES CLOSED FROM TRAFFIC CIRCLE TO 19TH ST E
(Sewer main installation)
Start: May 20, 9:00 a.m. End: May 27, 5:00 p.m.
WARMAN RD SB RAMP CLOSED AT CIRCLE DR E
(Construction)
Start: May 12, 7:00 a.m. End: June 1, 5:00 p.m.
CIRCLE DR W SB SPEED REDUCTION FROM GLENWOOD AVE TO 33RD ST W
(Jersey barrier placement)
Start: April 28, 7:00 a.m. End: June 2, 4:00 p.m.
BROADWAY AVE SB LANES CLOSED FROM SASKATCHEWAN CRES E TO 12TH ST E
(Link platform construction)
Start: May 20, 7:00 a.m. End: June 2, 4:30 p.m.
BOYCHUK DR SB CURB LANE CLOSED FROM 8TH ST E TO BRIARWOOD RD
(Sidewalk construction)
Start: May 16, 8:00 a.m. End: June 6, 5:00 p.m.
BRIGHTON BLVD ROAD CLOSED FROM TASKAMANWA ST TO 8TH ST E
(Construction)
Start: November 20, 7:00 a.m. End: September 26, 2025, 5:00 p.m.
BROADWAY BRIDGE CLOSED FROM 12TH ST E TO 20TH ST E
(Bridge rehabilitation)
Start: May 11, 7:00 p.m. End: October (Date TBA)
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.
Weekend Road Report - May 24-25, 2025
May 23, 2025 - 2:30pm
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
LORNE AVE SB LANES CLOSED FROM RUTH ST W TO JASPER AVE
(Sanitary sewer lining)
Two-way traffic will be maintained in NB lanes
Start: May 24, 7:00 a.m. End: May 24, 11:00 a.m.
BRIGHTON BLVD ROAD CLOSED FROM BRIGHTON COMMON TO TASKAMANWA ST
(Paving)
Start: May 24, 7:00 a.m. End: May 24, 9:00 p.m.
1ST AVE N NB/SB TURN LANE CLOSED FROM 25TH ST E TO 26TH ST E
(Sewer main lining)
Start: May 24, 8:00 p.m. End: May 25, 12:00 a.m.
RUTH ST W ROAD CLOSED FROM ST HENRY AVE TO HERMAN AVE
(Sask Marathon)
Start: May 25, 5:00 a.m. End: May 25, 1:30 p.m.
TAYLOR ST W ROAD CLOSED FROM ST HENRY AVE TO EASTLAKE AVE
(Sask Marathon)
Start: May 25, 5:00 a.m. End: May 25, 1:30 p.m.
TRAFFIC BRIDGE CLOSED FROM 11TH E ST TO 19TH ST E
(Sask Marathon)
Start: May 25, 5:00 a.m. End: May 25, 1:30 p.m.
VICTORIA AVE NB LANES CLOSED FROM 11TH ST E TO TAYLOR ST
(Sask Marathon)
Start: May 25, 5:00 a.m. End: May 25, 1:30 p.m.
SPADINA CRES E ROAD CLOSED FROM 2ND AVE TO 3RD AVE S
(Sask Marathon)
Start: May 25, 5:00 a.m. End: May 25, 1:30 p.m.
SPADINA CRES E NB LANES CLOSED FROM 20TH ST TO PINEHOUSE DR
(Sask Marathon)
Start: May 25, 5:00 a.m. End: May 25, 1:30 p.m.
3RD AVE S ROAD CLOSED FROM 19TH ST E TO 20TH ST E
(Sask Marathon)
Start: May 25, 5:00 a.m. End: May 25, 1:30 p.m.
20TH ST E EB LANES CLOSED FROM 3RD AVE S TO SPADINA CRES E
(Sask Marathon)
Start: May 25, 5:00 a.m. End: May 25, 1:30 p.m.
IDYLWYLD DR S SB CURB & RIGHT TURN BAY CLOSED AT 22ND ST W
(Catch basin replacement)
Start: May 25, 8:00 a.m. End: May 25, 5:00 p.m.
NIGHT WORK
IDYLWYLD DR S SB MEDIAN & CENTER LANES CLOSED AT 20TH ST W
(Sewer cleaning)
Start: May 25, 7:00 p.m. End: May 25, 11:00 p.m.
IDYLWYLD DR S NB MEDIAN LANE CLOSED FROM 20TH ST E TO 21ST ST E
(Sewer cleaning)
Start: May 25, 7:00 p.m. End: May 25, 11:00 p.m.
IDYLWYLD DR S NB MEDIAN LANE CLOSED FROM 21ST ST E TO 22ND ST E
(Sewer main lining)
Start: May 25, 8:00 p.m. End: May 26, 2:00 a.m.
ONGOING
22ND ST E WB LANES CLOSED AT 1ST AVE N
(Sewer main lining)
Start: May 23, 7:00 p.m. End: May 24, 1:00 a.m.
CUMBERLAND AVE S NB LANES CLOSED FROM TAYLOR ST E TO 5TH ST E
(Sidewalk replacements)
Two-way traffic will be maintained in the SB lanes
Start: May 12, 7:00 a.m. End: May 24, 5:00 p.m.
33RD ST E WB LANES CLOSED FROM QUEBEC AVE TO ONTARIO AVE
(Link platform installation)
Two-way traffic will be maintained in the EB lanes
Start: May 12, 7:00 a.m. End: May 25, 5:00 p.m.
3RD AVE S NB LANES CLOSED FROM TRAFFIC CIRCLE TO 19TH ST E
(Sewer main installation)
Start: May 20, 9:00 a.m. End: May 27, 5:00 p.m.
WARMAN RD SB RAMP CLOSED AT CIRCLE DR E
(Construction)
Start: May 12, 7:00 a.m. End: June 1, 5:00 p.m.
CIRCLE DR W SB SPEED REDUCTION FROM GLENWOOD AVE TO 33RD ST W
(Jersey barrier placement)
Start: April 28, 7:00 a.m. End: June 2, 4:00 p.m.
BROADWAY AVE SB LANES CLOSED FROM SASKATCHEWAN CRES E TO 12TH ST E
(Link platform construction)
Start: May 20, 7:00 a.m. End: June 2, 4:30 p.m.
BOYCHUK DR SB CURB LANE CLOSED FROM 8TH ST E TO BRIARWOOD RD
(Sidewalk construction)
Start: May 16, 8:00 a.m. End: June 6, 5:00 p.m.
BRIGHTON BLVD ROAD CLOSED FROM TASKAMANWA ST TO 8TH ST E
(Construction)
Start: November 20, 7:00 a.m. End: September 26, 2025, 5:00 p.m.
BROADWAY BRIDGE CLOSED FROM 12TH ST E TO 20TH ST E
(Bridge rehabilitation)
Start: May 11, 7:00 p.m. End: October (Date TBA)
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.