Daily Road Report - July 18, 2023
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
IDYLWYLD DR S NB MEDIAN LANE CLOSED AT TAYLOR ST W
(Deck testing)
Start: July 18, 12:00 a.m. End: July 18, 7:00 a.m.
CENTRAL AVE SB CURB LANE CLOSED FROM 103RD ST E TO COLLEGE DR
(Tree removal)
Closure will be set daily from 8:00 a.m. to 4:00 p.m.
Start: July 18, 8:00 a.m. End: July 19, 4:00 p.m.
DUNDONALD AVE ROAD CLOSED FROM DIEPPE ST TO MOUNTBATTEN ST
(Catch basin, manhole & ditch grating work)
Start: July 18, 8:00 a.m. End: July 24, 4:30 p.m.
PRESTON AVE N NB & SB MEDIAN LANES CLOSED FROM COLLEGE DR TO EAST RD
(Pole replacements)
Start: July 18, 9:00 a.m. End: July 18, 1:00 p.m.
NIGHTWORK
CIRCLE DR W WB LANES CLOSED FROM 1ST AVE N TO FAITHFULL AVE
(Road resurfacing)
Two-way traffic will be maintained in the EB lanes.
Start: July 17, 7:00 p.m. End: July 18, 6:00 a.m.
IDYLWYLD DR N NB CURB LANE CLOSED AT TAYLOR ST E
(Bridge testing)
Start: July 17, 7:00 p.m. End: July 18, 1:00 a.m.
IDYLWYLD DR N NB & SB MEDIAN LANES CLOSED FROM 39TH ST W TO 45TH ST W
(Bridge washing)
Start: July 18, 7:00 p.m. End: July 19, 6:00 a.m.
33RD ST W EB & WB CURB LANES CLOSED AT CIRCLE DR W
(Bridge inspection & testing)
Start: July 18, 7:00 p.m. End: July 19, 1:00 a.m.
CIRCLE DR W SB CURB LANE CLOSED AT 33RD ST W
(Bridge testing & inspection)
Start: July 18, 7:00 p.m. End: July 19, 1:00 a.m.
ONGOING
33RD ST E WB CURB LANE CLOSED FROM ONTARIO AVE TO ALBERT AVE
(Pedestrian ramp replacement)
Start: July 17, 9:00 a.m. End: July 18, 4:30 p.m.
33RD ST E WB CURB LANE CLOSED FROM QUEBEC AVE TO ONTARIO AVE
(Pedestrian ramp replacement)
Start: July 17, 7:00 a.m. End: July 18, 4:30 p.m.
CLARENCE AVE S NB & SB CURB LANES CLOSED AT CIRCLE DR S
(Bridge deck work)
Closure will be set daily from 9:00 a.m. to 3:00 p.m.
Start: July 17, 9:00 a.m. End: July 19, 3:00 p.m.
33RD ST W EB CURB LANE CLOSED AT EDMONTON AVE
(Pedestrian ramp replacement)
Start: July 17, 9:00 a.m. End: July 19, 5:00 p.m.
DUNDONALD AVE ROAD CLOSED FROM MOUNTBATTEN ST TO DIEPPE ST
(Catch basin & manhole installations)
Start: June 30, 8:00 a.m. End: July 20, 5:00 p.m.
WANUSKEWIN RD SB LANES CLOSED FROM 71ST ST E TO HIGHWAY 11
(Road resurfacing)
Start: July 17, 7:00 a.m. End: July 21, 7:00 p.m.
PRESTON AVE S SB LANES CLOSED FROM 14TH ST E TO MAIN ST
(Roadway paving)
Start: June 26, 7:00 a.m. End: July 29, 5:00 p.m.
BUTE ST ROAD CLOSED FROM BROADWAY AVE TO WILLIAM AVE
(Weaver Park storm sewer upgrades)
Broadway Ave intersection at Brute St closed
Start: July 6, 7:00 a.m. End: September 9, 5:00 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM OSLER ST TO COLLEGE DR
(Water main upgrades)
Start: July 10, 7:00 a.m. End: September 20, 5:00 p.m.
CIRCLE DR E EB LANES CLOSED FROM WARMAN RD TO PRESTON AVE N
(Bridge rehabilitation)
Two-way traffic will be maintained in the WB lanes
Start: June 25, 5:00 a.m. End: November 1, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.