Weekend Road Report - June 10-11, 2023
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
33RD ST W EB CURB LANE CLOSED FROM KENSINGTON BLVD TO ELK POINT RD
(Road work)
Start: June 10, 7:00 a.m. End: June 10, 4:30 p.m.
IDYLWYLD DR N SB MEDIAN CLOSED FROM 30TH ST W TO 28TH ST W
(Sewer lining)
Start: June 10, 7:00 a.m. End: June 10, 7:00 p.m.
TAYLOR ST E WB CURB & NEXT LANE CLOSED FROM CIRCLE DR E TO ARLINGTON AVE
(Sewer lining)
Start: June 10, 7:00 a.m. End: June 10, 7:00 p.m.
AVE C N ROAD CLOSED FROM 33RD ST W TO 32ND ST W
(4th Quarter Vintage Event)
Start: June 10, 8:00 a.m. End: June 10, 6:00 p.m.
CIRCLE DR E WB LANES CLOSED FROM WARMAN RD TO MILLAR AVE
(Catch basin repairs)
Two-way traffic will be maintained in the EB Lanes
Start: June 10, 8:00 a.m. End: June 11, 3:00 p.m.
22ND ST W EB TO NB RAMP CLOSED FROM CIRCLE DR W TO 22ND ST W
(Streetlight pole replacement)
Start: June 11, 6:00 a.m. End: June 11, 11:00 a.m.
33RD ST W RAMP TO CIRCLE DR SB CLOSED AT CIRCLE DR W
(Streetlight pole replacement)
Start: June 11, 7:00 a.m. End: June 11, 12:00 p.m.
TAYLOR ST E WB LANES & SB CURB LANE CLOSED AT BROADWAY AVE
(Roadway patching)
Start: June 11, 7:00 a.m. End: June 11, 3:00 p.m.
PRESTON AVE S NB LEFT TURN LANE & THROUGH LANE CLOSED AT TAYLOR ST E
(Roadway patching)
Start: June 11, 7:00 a.m. End: June 11, 5:00 p.m.
2ND AVE N NB LANE & SB LEFT TURN LANE CLOSED FROM QUEEN ST TO KING ST
(Roadway patching)
Start: June 11, 8:00 a.m. End: June 11, 4:00 p.m.
LORNE AVE SB LANES & NB MEDIAN LANE CLOSED FROM EXHIBITION GROUNDS RD TO JASPER AVE
(Roadway patching)
Start: June 11, 8:00 a.m. End: June 11, 4:00 p.m.
CLARENCE AVE S NB CURB LANE CLOSED AT 14TH ST E
(Roadway patching)
Start: June 11, 8:00 a.m. End: June 11, 4:00 p.m.
NIGHTWORK
CIRCLE DR E EB LEFT TURN LANE CLOSED AT FAITHFULL AVE
(Durable pavement marking)
Start: June 11, 7:00 p.m. End: June 12, 5:00 a.m.
CIRCLE DR E EB LEFT TURN LANES CLOSED FROM 1ST AVE N TO VENTURE CRES
(Durable pavement marking)
Start: June 11, 7:00 p.m. End: June 12, 5:00 a.m.
CIRCLE DR E EB LEFT TURN LANE CLOSED AT MILLAR AVE
(Durable pavement marking)
Start: June 11, 7:00 p.m. End: June 12, 5:00 a.m.
CIRCLE DR E EB MEDIAN, CENTRE & LEFT TURN LANES CLOSED FROM AVE C N TO ALBERTA AVE
(Durable pavement markings)
Start: June 11, 7:00 p.m. End: June 12, 5:00 a.m.
IDYLWYLD DR N NB MEDIAN & LEFT TURN LANES CLOSED FROM 31ST ST E TO 39TH ST E
(Durable pavement markings)
Start: June 10, 7:00 p.m. End: June 11, 5:00 a.m.
IDYLWYLD DR N SB MEDIAN & LEFT TURN LANES FROM 33RD ST W TO 25TH ST E
(Durable pavement markings)
Start: June 10, 7:00 p.m. End: June 11, 5:00 a.m.
IDYLWYLD DR N NB & SB MEDIAN & CENTER LANES CLOSED FROM 25TH ST E TO 20TH ST E
(Durable pavement markings)
Start: June 9, 7:00 p.m. End: June 10, 5:00 a.m.
MCKERCHER DR NB & SB MEDIAN LANES CLOSED FROM DEGEER ST TO 8TH ST E
(Cleaning Sanitary Lines)
Start: June 9, 9:00 p.m. End: June 10, 8:00 a.m.
ONGOING
CUMBERLAND AVE S SB LANES CLOSED FROM MAIN ST TO 8TH ST E
(Road rehabilitation)
Two-way traffic will be maintained in NB lanes
Start: June 8, 10:00 a.m. End: June 10, 4:30 p.m.
PRESTON AVE S SB LANES CLOSED FROM 14TH ST E TO MAIN ST
(Roadway paving)
Two-way traffic will be maintained in the NB lanes
Start: May 29, 10:00 a.m. End: June 16, 5:00 p.m.
BALTZAN BLVD ROAD CLOSED AT HORNER CRES
(Building construction)
Start: June 5, 7:00 a.m. End: June 17, 5:00 p.m.
CUMBERLAND AVE S ROAD CLOSED FROM ISABELLA ST E TO ADELAIDE ST E
(Service connection replacements)
Start: June 5, 7:00 a.m. End: June 19, 5:00 p.m.
MCORMOND DR NB CURB LANE CLOSED AT STENSRUD RD
(Pavement & curb work)
Start: May 15, 7:00 a.m. End: June 23, 4:00 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM COLONY ST TO AIRD ST
(Water main work)
Start: May 18, 7:00 a.m. End: June 23, 7:00 p.m.
CIRCLE DR E WB LANES CLOSED FROM ATTRIDGE DR TO WARMAN RD
(Bridge rehabilitation)
Two-way traffic will be maintained across Circle Drive North Bridge. Max Load width is 4.5m
Start: February 28, 6:00 a.m. End: June 24, 7:00 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM TEMPERANCE ST TO UNIVERSITY DR
(Construction)
Start: May 1, 7:00 a.m. End: June 25, 5:00 p.m.
RUTH ST E ROAD CLOSED FROM EASTLAKE AVE TO BROADWAY AVE
(Storm sewer installation)
Start: May 23, 7:00 a.m. End: July 3, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.