Daily Road Report - July 21, 2023
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
CIRCLE DR S NB, SB & EB MEDIAN LANES & WB LEFT TURN LANE CLOSED AT 11TH ST W
(Deck testing & inspection)
Start: July 21, 1:00 a.m. End: July 21, 6:00 a.m.
3RD AVE N SB CURB LANE CLOSED FROM 23RD ST E TO 22ND ST E
(Infrastructure upgrade)
Start: July 21, 7:00 a.m. End: July 21, 5:00 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM AIRD ST TO OSLER ST
(Water main work)
Start: July 21, 7:00 a.m. End: September 29, 6:00 p.m.
22ND ST E ROAD CLOSED FROM 2ND AVE N TO 3RD AVE N
(Temporary water line installation)
Start: July 21, 9:30 a.m. End: July 21, 11:00 a.m.
3RD AVE S ROAD CLOSED FROM 21ST ST E TO 22ND ST E
(Temporary water line installation)
Start: July 21, 11:00 a.m. End: July 21, 12:30 p.m.
NIGHTWORK
CIRCLE DR W WB LANES CLOSED FROM QUEBEC AVE TO NORTHRIDGE DR
(Roadway paving)
Two-way traffic will be maintained in the EB lanes
Start: July 20, 7:00 p.m. End: July 21, 6:00 a.m.
CIRCLE DR E NB CURB LANE CLOSED FROM 8TH ST E TO 14TH ST E
(Road resurfacing)
8th St Ramp to Circle Dr NB closed
Start: July 21, 7:00 p.m. End: July 22, 6:00 a.m.
ONGOING
WANUSKEWIN RD SB LANES CLOSED FROM 71ST ST E TO HIGHWAY 11
(Road resurfacing)
Start: July 17, 7:00 a.m. End: July 21, 7:00 p.m.
DUNDONALD AVE ROAD CLOSED FROM DIEPPE ST TO MOUNTBATTEN ST
(Catch basin, manhole & ditch grating work)
Start: July 18, 8:00 a.m. End: July 24, 4:30 p.m.
PRESTON AVE S SB LANES CLOSED FROM 14TH ST E TO MAIN ST
(Roadway paving)
Start: June 26, 7:00 a.m. End: July 29, 5:00 p.m.
BUTE ST ROAD CLOSED FROM BROADWAY AVE TO WILLIAM AVE
(Weaver park upgrades)
Broadway Ave intersection at Brute St closed
Start: July 6, 7:00 a.m. End: September 9, 5:00 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM OSLER ST TO COLLEGE DR
(Water main upgrades)
Start: July 10, 7:00 a.m. End: September 20, 5:00 p.m.
CIRCLE DR E EB LANES CLOSED FROM WARMAN RD TO PRESTON AVE N
(Bridge rehabilitation)
Two-way traffic will be maintained in the WB lanes
Start: June 25, 5:00 a.m. End: November 1, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.