Daily Road Report, July 4, 2023
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
2ND AVE S SB LANES CLOSED FROM 22ND ST E TO 21ST ST E
(Vault backfilling)
Start: July 4, 7:00 a.m. End: July 4, 4:30 p.m.
CUMBERLAND AVE S ROAD CLOSED FROM 1ST ST E TO TAYLOR ST E
(Connection replacement)
Start: July 4, 7:00 a.m. End: July 10, 5:00 p.m.
BROADWAY AVE SB PARKING LANE CLOSED FROM HOPKINS ST TO WILSON CRES
(Roadway work)
Start: July 4, 9:00 a.m. End: July 4, 3:00 p.m.
PRESTON AVE N NB & SB MEDIAN LANES CLOSED FROM 108TH ST W TO PERIMETER RD
(Traffic pole installation)
Start: July 4, 9:00 a.m. End: July 4, 3:00 p.m.
8TH ST E EB CURB LANE CLOSED FROM MCKINNON AVE N TO CAIRNS AVE
(Brushing)
Start: July 4, 9:00 a.m. End: July 4, 5:00 p.m.
ONGOING
DIEFENBAKER DR SB CURB & CENTER LANE CLOSED FROM 22ND ST W TO FAIRLIGHT DR
(Sidewalk infill)
Start: June 20, 7:00 a.m. End: July 4, 6:00 p.m.
MCORMOND DR NB CURB LANE CLOSED AT STENSRUD RD
(Pavement & Curb work)
Start: May 15, 7:00 a.m. End: July 7, 4:00 p.m.
MELVILLE ST WB LANES CLOSED FROM JASPER AVE S TO LORNE AVE
(Cable work)
Start: July 3, 7:00 a.m. End: July 7, 4:30 p.m.
AVE H N NB & SB LANES CLOSED AT 31ST ST W
(Sewer lining)
Start: June 12, 9:00 a.m. End: July 12, 3:00 p.m.
DUNDONALD AVE ROAD CLOSED FROM MOUNTBATTEN ST TO DIEPPE ST
(Catch basin & manhole installations)
Start: June 30, 8:00 a.m. End: July 20, 5:00 p.m.
PRESTON AVE S SB ROAD CLOSED FROM 14TH ST E TO MAIN ST
(Roadway paving)
Start: June 26, 7:00 a.m. End: July 29, 5:00 p.m.
2ND AVE N NB PARKING LANE CLOSED FROM 26TH ST E TO QUEEN ST
(Building construction)
Start: June 12, 6:00 a.m. End: August 1, 4:30 p.m.
CIRCLE DR E EB LANES CLOSED FROM WARMAN RD TO PRESTON AVE N
(Bridge rehabilitation)
Two-way traffic will be maintained in the WB lanes
Start: June 25, 5:00 a.m. End: November 1, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.