NEW
DIEFENBAKER DR SB CURB & CENTER LANES CLOSED FROM 22ND ST W TO FAIRLIGHT DR
(Sidewalk infill)
Start: June 20, 7:00 a.m. End: July 4, 6:00 p.m.
PRESTON AVE S SB CURB LANE CLOSED FROM WILLIS CRES TO CORNISH RD
(Sanitary cleaning)
Start: June 20, 9:00 a.m. End: June 20, 11:00 a.m.
CIRCLE DR W SPEED REDUCTION AT AIRPORT DR
(Sanitary sewer lining)
Start: June 20, 9:00 a.m. End: June 20, 3:00 p.m.
MCKERCHER DR NB MEDIAN LANE CLOSED FROM DUNCAN CRES TO MOUNT ALLISON CRES
(Manhole repair)
Start: June 20, 9:00 a.m. End: June 20, 5:00 p.m.
PRESTON AVE S SB MEDIAN LANE CLOSED FROM CORNISH RD TO STONEBRIDGE COMMON
(Sanitary pipe cleaning)
Start: June 20, 11:30 a.m. End: June 20, 3:30 p.m.
CIRCLE DR E SB SPEED REDUCTION FROM LOUISE ST TO 8TH ST E
(Litter removal)
Start: June 20, 1:00 p.m. End: June 20, 3:00 p.m.
NIGHTWORK
CIRCLE DR S EB & WB MEDIAN LANES CLOSED FROM LORNE AVE TO SPADINA CRES W
(Bridge washing)
Start: June 20, 8:00 p.m. End: June 21, 6:00 a.m.
ONGOING
3RD AVE S NB CURB LANE CLOSED FROM 20ST ST E TO 22ND ST E
(Infrastructure upgrades)
Start: June 19, 7:00 a.m. End: June 21, 4:30 p.m.
HART RD ROAD CLOSED FROM BETTS AVE TO SHILLINGTON CRES
(Construction)
Start: June 19, 7:00 a.m. End: June 21, 6:00 p.m.
MCORMOND DR NB CURB LANE CLOSED AT STENSRUD RD
(Pavement & curb work)
Start: May 15, 7:00 a.m. End: June 23, 4:00 p.m.
CIRCLE DR E WB CURB CLOSED AT 1ST AVE N
(Valve removal)
Start: June 19, 7:00 a.m. End: June 23, 4:30 p.m.
1ST AVE N ROAD CLOSED FROM CIRCLE DR E TO 42ND ST E
(Valve removal)
Start: June 19, 7:00 a.m. End: June 23, 4:30 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM COLONY ST TO AIRD ST
(Water main work)
Start: May 18, 7:00 a.m. End: June 23, 7:00 p.m.
CIRCLE DR E WB LANES CLOSED FROM ATTRIDGE DR TO WARMAN RD
(Bridge rehabilitation)
Two-way traffic will be maintained across Circle Drive North Bridge. Max Load width is 4.5m
Start: February 28, 6:00 a.m. End: June 24, 7:00 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM TEMPERANCE ST TO UNIVERSITY DR
(Construction)
Start: May 1, 7:00 a.m. End: June 25, 5:00 p.m.
PRESTON AVE S SB LANES CLOSED FROM MAIN ST TO 8TH ST E
(Road resurfacing)
Two-way traffic will be maintained in the NB lanes.
Start: June 19, 7:00 a.m. End: June 25, 5:00 p.m.
8TH ST E WB CURB LANE CLOSED AT PRESTON AVE S
(Road resurfacing)
Start: June 19, 7:00 a.m. End: June 25, 5:00 p.m.
CUMBERLAND AVE S ROAD CLOSED FROM 5TH ST E TO 3RD ST E
(Connection replacement)
Start: June 14, 7:00 a.m. End: June 25, 5:00 p.m.
CUMBERLAND AVE S ROAD CLOSED FROM 3RD ST E TO 1ST ST E
(Connection replacement)
Start: June 14, 7:00 p.m. End: June 25, 5:00 p.m.
RUTH ST E ROAD CLOSED FROM EASTLAKE AVE TO BROADWAY AVE
(Storm sewer installation)
Start: May 23, 7:00 a.m. End: June 26, 5:00 p.m.
HORNER CRES ROAD CLOSED AT BALTZAN BLVD
(Crane lift)
Start: June 19, 7:00 a.m. End: June 30, 5:00 p.m.
MCORMOND DR NB CURB LANE CLOSED FROM HORNER CRES TO BALTZAN BLVD
(Ramp tie in)
Start: June 19, 1:00 p.m. End: July 2, 4:30 p.m.
NEAULT RD SB RIGHT TURN BAY CLOSED FROM 33RD ST W TO 22ND ST W
(Storm sewer upgrades)
Start: June 19, 7:00 a.m. End: July 3, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.