Daily Road Report - May 2, 2023
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
LORNE AVE SB CURB LANE CLOSED FROM ASH ST E TO RUTH ST E
(Bridge maintenance)
Start: May 2, 7:00 a.m. End: May 2, 1:00 p.m.
RUTH ST W EB MEDIAN LANE CLOSED FROM ST GEORGE AVE TO LORNE AVE
(Bridge maintenance)
Start: May 2, 7:00 a.m. End: May 2, 1:00 p.m.
ONGOING
33RD ST W ROAD CLOSED FROM AVE K N TO AVE L N
(Catch basin & manhole work)
Start: May 1, 9:00 a.m. End: May 2, 4:30 p.m.
2ND AVE S ROAD CLOSED FROM 22ND ST E TO 21ST ST E
(Vault construction)
Start: May 1, 7:00 a.m. End: May 5, 5:00 p.m.
BALTZAN BLVD ROAD CLOSED AT HORNER CRES
(Building construction)
Start: April 17, 7:00 a.m. End: May 5, 5:00 p.m.
22ND ST E ROAD CLOSED FROM 3RD AVE N TO 4TH AVE N
(Infrastructure upgrades)
Start: May 1, 7:00 a.m. End: May 25, 5:00 p.m.
CIRCLE DR E WB FROM ATTRIDGE DR TO WARMAN RD
(Bridge Rehab)
Two-Way traffic will be maintained across the Bridge. Max Load width is 4.5m
Start: February 28, 6:00 a.m. End: June 10, 7:00 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM TEMPERANCE ST TO UNIVERSITY DR
(Construction)
Start: May 1, 7:00 a.m. End: June 25, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.