Daily Road Report - October 30, 2023
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
1ST AVE N NB MEDIAN & LEFT TURN LANES CLOSED FROM 22ND ST E TO 23RD ST E
(Sewer lining)
Start: October 30, 9:00 a.m. End: October 30, 3:00 p.m.
33RD ST W EB & WB MEDIAN LANES CLOSED AT AVE I N
(Sewer lining)
Start: October 30, 9:00 a.m. End: October 30, 3:00 p.m.
FAIRLIGHT DR WB CURB LANE CLOSED FROM DIEFENBAKER DR TO GROPPER CRES
(Street light replacement)
Start: October 30, 10:00 a.m. End: October 30, 1:00 p.m.
ONGOING
4TH AVE S SB MEDIAN LANE CLOSED AT 19TH ST E
(SL&P manhole repair)
Start: September 18, 7:00 a.m. End: November 1, 5:00 p.m.
MELVILLE ST INTERSECTION CLOSED AT PORTAGE AVE
(SaskEnergy construction)
Start: October 23, 7:00 a.m. End: November 3, 5:00 p.m.
MCORMOND DR SB CLOSED FROM BRIGHTON CIRCLE TO BRIGHTON COMMON
(Jersey barrier relocation)
Start: October 4, 7:00 a.m. End: November 8, 7:00 a.m.
BALTZAN BLVD ROAD CLOSED FROM HORNER CRES TO ORBAN WAY
(Service connections)
Start: October 25, 7:00 a.m. End: November 8, 6:00 p.m.
22ND ST E EB CURB & CENTER LANE CLOSED FROM AUDITORIUM AVE TO 1ST AVE S
(Vault repairs)
Start: September 11, 7:00 a.m. End: November 30, 4:00 p.m.
NEAULT RD ROAD CLOSED FROM 22ND ST W TO WHELAN RD
(Construction)
Start: July 24, 7:00 a.m. End: December 15, 4:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.