Daily Road Report, October 5, 2023
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
FAIRLIGHT DR SB LANES CLOSED FROM MCCORMACK RD TO 11TH ST W
(Crack sealing)
Two-way traffic in NB lanes.
Start: October 5, 7:00 a.m. End: October 5, 12:00 p.m.
22ND ST W WB CURB LANE CLOSED AT AVE H N
(Environmental monitoring)
Start: October 5, 9:00 a.m. End: October 5, 10:00 a.m.
CIRCLE DR W NB & SB MEDIAN LANE CLOSED FROM 33RD ST W TO AIRPORT DR
(Litter pick up)
Start: October 5, 9:00 a.m. End: October 5, 12:00 p.m.
WARMAN RD NB & SB CURB & CENTER LANES CLOSED AT CIRCLE DR E
(Bridge Maintenance)
Start: October 5, 9:00 a.m. End: October 5, 3:00 p.m.
ONGOING
MELVILLE ST INTERSECTION CLOSED AT JASPER AVE
(Infrastructure upgrades)
Start: August 8, 7:00 a.m. End: October 7, 5:00 p.m.
SPADINA CRES E ROAD CLOSED FROM 20TH ST E TO 22ND ST E
(Infrastructure upgrades)
Start: October 2, 7:00 a.m. End: October 8, 5:30 p.m.
BROADWAY AVE ROAD CLOSED FROM 5TH ST E TO 8TH ST E
(Water main work)
Start: September 11, 7:00 a.m. End: October 15, 4:30 p.m.
ZIMMERMAN RD NB & SB CURB LANES CLOSED FROM MARKET DR TO MEADOWS PKY
(Sidewalk installation)
Start: September 25, 8:00 a.m. End: October 15, 5:00 p.m.
MCORMOND DR SB ROAD CLOSED FROM BRIGHTON CIRCLE TO BRIGHTON COMMON
(Jersey barrier relocation)
Start: October 4, 7:00 a.m. End: October 17, 7:00 a.m.
4TH AVE S SB MEDIAN LANE CLOSED AT 19TH ST E
(SL&P manhole repair)
Start: September 18, 7:00 a.m. End: October 20, 5:00 p.m.
NEAULT RD ROAD CLOSED FROM 22ND ST W TO WHELAN RD
(Construction)
Start: July 24, 7:00 a.m. End: November 3, 4:00 p.m.
22ND ST E EB CURB & CENTER LANE CLOSED FROM AUDITORIUM AVE TO 1ST AVE S
(Vault repairs)
Start: September 11, 7:00 a.m. End: November 30, 4:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.