AVE H N INTERSECTION CLOSED AT 36TH ST W
(Roadway patching)
Start: September 20, 7:00 a.m. End: September 20, 3:00 p.m.
20TH ST W EB & WB MEDIAN LANES CLOSED FROM AVE N S TO AVE O S
(Roadway patching)
Start: September 20, 7:00 a.m. End: September 20, 3:00 p.m.
TAYLOR ST E EB MEDIAN LANE CLOSED FROM BROADWAY AVE TO WILLIAM AVE
(Construction)
Start: September 20, 9:00 a.m. End: September 20, 12:00 p.m.
PRESTON AVE S NB LEFT TURN LANE CLOSED AT TAYLOR ST E
(Traffic signal work)
Start: September 20, 9:00 a.m. End: September 20, 12:30 p.m.
MCKERCHER DR SB CURB & NEXT LANE CLOSED FROM COLLEGE DR TO BOYCHUK DR
(Streetlight pole replacements)
Start: September 20, 9:00 a.m. End: September 20, 2:00 p.m.
ONGOING
DUNDONALD AVE ROAD CLOSED FROM MOUNTBATTEN ST TO DIEPPE ST
(Catch basin & manhole installations)
Start: September 5, 8:00 a.m. End: September 20, 5:00 p.m.
HIGHWAY 11 NB CURB LANE CLOSED FROM CIRCLE DR E TO HIGHWAY 16
(Bridge maintenance)
Start: September 19, 9:00 a.m. End: September 22, 3:00 p.m.
BALTZAN BLVD ROAD CLOSED FROM HORNER CRES TO ORBAN WAY
(Service connections)
Start: September 11, 7:00 a.m. End: September 22, 4:30 p.m.
2ND AVE N NB CURB LANE CLOSED FROM QUEEN ST TO KING ST
(Sidewalk repairs)
Start: September 18, 7:00 a.m. End: September 22, 5:00 p.m.
SPADINA CRES E NB LANES CLOSED FROM 22ND ST E TO 23RD ST E
(Storm pipe repair)
Start: September 19, 7:00 a.m. End: September 29, 4:30 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM AIRD ST TO OSLER ST
(Contractor work)
Start: July 21, 7:00 a.m. End: September 29, 6:00 p.m.
MELVILLE ST INTERSECTION CLOSED AT JASPER AVE
(Infrastructure upgrades)
Start: August 8, 7:00 a.m. End: October 7, 5:00 p.m.
BROADWAY AVE NB & SB CLOSED FROM 5TH ST E TO 8TH ST E
(watermain work)
Start: September 11, 7:00 a.m. End: October 15, 4:30 p.m.
4TH AVE S SB MEDIAN LANE CLOSED AT 19TH ST E
(SL&P manhole repair)
Start: September 18, 7:00 a.m. End: October 20, 5:00 p.m.
CIRCLE DR E EB LANES CLOSED FROM WARMAN RD TO PRESTON AVE N
(Bridge rehabilitation)
Two-way traffic will be maintained in the WB lanes.
Start: June 25, 5:00 a.m. End: November 1, 5:00 p.m.
NEAULT RD ROAD CLOSED FROM 22ND ST W TO WHELAN RD
(Construction)
Start: July 24, 7:00 a.m. End: November 3, 4:00 p.m.
22ND ST E EB CURB & CENTER LANE FROM AUDITORIUM AVE TO 1ST AVE S
(Vault Repairs)
Start: September 11, 7:00 a.m. End: November 30, 4:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.